HORIZONMarkets
01

Complete project overview

RERA Bihar · Registration filing
Units
24 units
Unit mix
24 × 3 BHK
Parking
24 spaces
Land area
1,113 sq m
Built-up area
2,766 sq m

Timeline

Project startedOct 2022
RERA registeredJan 2023
Proposed completionDec 2025
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

24 units across 6 batches
BuildingTypeArea sq mCount
Kaushal Kishor Heritage3 BHK2354
Kaushal Kishor Heritage3 BHK2714
Kaushal Kishor Heritage3 BHK2844
Kaushal Kishor Heritage3 BHK2364
Kaushal Kishor Heritage3 BHK2384
Kaushal Kishor Heritage3 BHK2104

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RERA Bihar · Promoter registration

SK BUILDERS & COLONISOR PRIVATE LIMITED

CompanyPromoter type
Patna, BiharBased in
---Select---Also RERA-registered in
9Projects
2Cities
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
506 homeson the public record across 9 projects
46,720 sq mbuilt-up filed
20,000 sq mland declared
₹116.52 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Nagar Parisad Danapur NizamatMunicipal / Corporationthis project2 of 3 projects
sfdsf1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Bihar · Registration filing
District
Patna
Anchal (block)
Danapur
Mauja (revenue village)
Mustaphpur
Address
Plot No.- 901, Khata No.- 31, Thana No.- 36, Thana- Danapur, Mauza- Mustafapur, Dist- Patna
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.4km away · Clinic within 2km
LifestylePark 1.4km away · Gym or sports centre 1.5km away
ShoppingSupermarket 1.5km away
Getting around
Expressway 1.4 kmPrimary road 2.1 km · Neora RoadRailway line 1.3 kmRailway station 2.2km away (Danapur)Limited bus connectivity nearby
Water & environment
Water body 934 m · chhat puja talabCanal 1.5 km · Barun Canal
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹5.26 Cr declared to build 24 flats. What that works out to:

₹21.92 Lakhdeclared cost per flatall-in — land + construction
₹1,767/sq ftof built-up area₹19,018/sq m
4%of the cost is land₹167/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Bihar · Approved building plan

Nagar Parisad Danapur Nizamat

Municipal / Corporation
Building Permitapproved 9 Dec 2022 · 3 yrs ago

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Bihar does not publish quarterly progress reports. How far along it actually is cannot be read here.