Complete project overview

MahaRERA · Registration filing
Floors
12
Buildings
2
Parking
70 spaces
Land area
1,562 sq m
Sanctioned built-up
6,268 sq m

Timeline

RERA registeredJul 2023
Proposed completionSep 2026
TodayJul 2026
Construction progress
Podiums0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Internal finishes30%
Stairs & lifts65%
Superstructure90%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Street Lighting100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SHREE BALAJI DEVELOPERS

PartnershipPromoter type
Nashik, MAHARASHTRABased in
21Projects
14Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
747 homes · 460 plotson the public record across 21 projects
69,014 sq mbuilt-up filed
31,413 sq mland declared
₹81.92 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Nashik Municipal CorporationMunicipal Corporationthis project4 of 13 projects
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 13 projects
BhopalTown & Country Planning (DTCP)1 of 13 projects
BurhanpurTown & Country Planning (DTCP)1 of 13 projects
Kalyan Dombivli Municipal CorporationMunicipal Corporation1 of 13 projects
Navi Mumbai Mumncipal Corporation1 of 13 projects
Pimpri Chinchwad Municipal CorporationMunicipal Corporation1 of 13 projects
Surat Municipal CorporationMunicipal / Corporation1 of 13 projects
Uran Municipal CouncilMunicipal Council1 of 13 projects
Vadodara Urban Development AuthorityUrban Development Authority1 of 13 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Aanandwali
Taluka
Nashik
District
Nashik
Pincode
422013
Survey no.
Survey No.26/6/2A+B/1+2+3, Plot No.4
North boundary
Adjoining Survey No 26 9 Part
East boundary
Adjoining Survey No 26 Part
South boundary
18 Mtr Colony Road
West boundary
Plot No 3
What’s nearby
SchoolsNearest school 1.1km away · Library 1.4km away
HealthcareHospital 1.0km away
LifestyleNo parks within 2km
ShoppingSupermarket 454m away
Getting around
Expressway 1.1 kmPrimary road 1.1 km · Gangapur RoadNo metro or railway within 5kmLimited bus connectivity nearby
04

Planning authority

MahaRERA · Approved building plan

Nashik Municipal Corporation

Municipal Corporation
Building Permit
Survey no. Survey No.26/6/2A+B/1+2+3, Plot No.4
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Nashik Municipal Corporation

Municipal corporation

Has approved 821 RERA projectsabout 1 in 24 in Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
692
On record
4,331 flats · 111 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.