01

Complete project overview

MahaRERA · Registration filing
Floors
5
Buildings
2
Parking
263 spaces
Land area
11,042 sq m
Sanctioned built-up
4,750 sq m

Timeline

RERA registeredApr 2026
Proposed completionDec 2031
TodayJul 2026
Construction progress
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Fire protection an…0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Champalal Kanhaiyalal Khinvasara

IndividualPromoter type
Aurangabad, MAHARASHTRABased in
6Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
145 homes · 322 plotson the public record across 6 projects
10,904 sq mbuilt-up filed
31,463 sq mplotted area
53,547 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Garkheda
Taluka
Aurangabad
District
Aurangabad
Pincode
431005
Survey no.
Plot No 21 and 22 CTS No 15736/135/3, Ulkanagari, Garkheda
North boundary
7 M Wide Road
East boundary
18 M Wide DP Road
South boundary
Plot No 23, 40, OS
West boundary
Open Space
What’s nearby
Schools1 school within 500m · College or university 1.2km away
HealthcareHospital 251m away · 2 clinics within 1km
LifestylePark 579m away · Gym or sports centre 852m away
ShoppingSupermarket 637m away · Mall 842m away · Bank 912m away
Getting around
Expressway 1.3 km · Jalna RoadPrimary road 1.9 km · Kranti ChowkRailway line 1.4 kmRailway station 2.5km away (Mukundawadi)Limited bus connectivity nearby
04

Planning authority

MahaRERA · Approved building plan

Chhatrapati Sambhajinagar Mahanagarpalika

Building Permit
Survey no. Plot No 21 and 22 CTS No 15736/135/3, Ulkanagari, Garkheda
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.