Complete project overview

MahaRERA · Registration filing
Floors
6
Buildings
2
Parking
20 spaces
Land area
326 sq m
Sanctioned built-up
975 sq m

Timeline

RERA registeredMar 2024
Proposed completionAug 2026
TodayJul 2026
Construction progress
Podiums0%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Water Supply100%
Sewerage (Chamber,…100%
Water conservation…100%
Fire protection an…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

KHUSHI BUILDCON

PartnershipPromoter type
Solapur, MAHARASHTRABased in
2Projects
2Cities
2023–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
224 homeson the public record across 2 projects
975 sq mbuilt-up filed
5,308 sq mland declared
₹18.72 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Solapur Municipal CorporationMunicipal Corporationthis project1 of 2 projects
Surat Urban Development AuthorityUrban Development Authority1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Solapur (M Corp.)
Taluka
Solapur North
District
Solapur
Pincode
413002
Survey no.
CITY SERVEY NO 1184 / B+C+D+E
North boundary
WIDE ROAD
East boundary
CTS NO 1186 1187 1188
South boundary
1179A 1 1308
West boundary
CTS NO 1180 1182B
What’s nearby
Schools1 school within 1km · College or university 1.2km away
HealthcareHospital 162m away · 5 clinics within 1km · Doctor's clinic within 1km
LifestylePark 1.9km away
ShoppingNo supermarket within 2km
Getting around
Expressway 818 m · Gulbarga - Solapur HighwayPrimary road 273 mRailway line 1.2 kmRailway station 1.7km away (Solapur)2 bus stops within 500m
Water & environment
Canal 1.3 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Solapur Municipal Corporation

Municipal Corporation
Building Permit
Survey no. CITY SERVEY NO 1184 / B+C+D+E
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Solapur Municipal Corporation

Municipal corporation

Has approved 66 RERA projects0.3% of Maharashtra.

an apartments market97% apartments · 3% plotted layouts. Apartments like yours are this body's core business.

Builders
60
On record
617 flats · 102 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.