Complete project overview

MahaRERA · Registration filing
Units
68 units
Mix
45 × Office · 23 × Shop
Carpet area
22–75 sq mper-unit range, as filed
Floors
4
Buildings
2
Parking
604 spaces
Land area
17,700 sq m
Sanctioned built-up
25,534 sq m

Timeline

RERA registeredNov 2022
Proposed completionDec 2024
TodayJul 2026
Construction progress
Podiums0%
Water conservation…0%
Flat fit-out55%
Storm Water Drains55%
OC-readiness65%
Stairs & lifts80%
Water Supply85%
Sewerage (Chamber,…85%
Internal finishes90%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
External finishes100%
Internal Roads & F…100%
Landscaping & Tree…100%
Street Lighting100%
Treatment And Disp…100%
Solid Waste Manage…100%
Energy managemcnt100%
Fire protection an…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.

Find your unit

Filed by type and size, in the batches the promoter registered — not a per-unit listing. Look yours up.

68 units across 15 batches
TypeArea sq mCount
Office4924
Office253
Office223
Shop411
Office483
Shop494
Shop734
Shop461
Shop331
Office451
Shop451
Office561
Shop561
Office7510
Shop7510

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

Supreme Developers

PartnershipPromoter type
Pune, MAHARASHTRABased in
4Projects
3Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
287 homeson the public record across 4 projects
38,802 sq mbuilt-up filed
27,723 sq mland declared
₹10.00 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Pimpale Saudagar
Taluka
Haveli
District
Pune
Pincode
411027
Survey no.
S. No 70 (Part)
North boundary
By 45 Mtr DP Road
East boundary
By 20 Mtr DP Road
South boundary
By Primary School Reservation
West boundary
By S No 71
What’s nearby
Schools1 school within 1km
HealthcareHospital 581m away · 6 clinics within 1km · Pharmacy within 1km
LifestylePark 832m away · Gym or sports centre 668m away · 29+ restaurants and cafes within 1km
ShoppingSupermarket 1.3km away · Mall 1.9km away · Bank 96m away
Getting around
Expressway 2.6 km · Old Mumbai Pune HighwayPrimary road 50 m · Wakad - Nashik Phata BRTS Road | Wakad - Bhosari BRTS Road | Nashik Phata RoadRailway line 2.3 km · Mumbai–Pune RailwayMetro station 2.6km away (Sant Tukaram Nagar)Bus stop within 500m
Water & environment
River 558 m · Pavana RiverWater body 617 m
distances only — not a flood assessment
Legal & regulatory record
Litigation4 cases on record, earliest 2010
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.