HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
22
Buildings
2
Parking
74 spaces
Land area
6,319 sq m
Sanctioned built-up
12,675 sq m
Recreational open space
635 sq m

Timeline

RERA registeredOct 2023
Proposed completionDec 2028
TodayJul 2026
Construction progress
Flat fit-out0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Community Building…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
External finishes15%
Internal finishes50%
Stairs & lifts70%
Superstructure90%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Konnark High Castle

PartnershipPromoter type
Raigarh, MAHARASHTRABased in
1Projects
1City
2023–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Giravale
Taluka
Panvel
District
Raigarh
Pincode
410221
Survey no.
Gut No 59 & 60
North boundary
64
East boundary
61
South boundary
54
West boundary
57
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.1km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 688 mPrimary road 1.3 kmRailway line 1.0 km · Konkan RailwayRailway station 1.2km away (Somatne)Limited bus connectivity nearby
Water & environment
River 809 mWater body 1.9 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Maharashtra State Road Developement Corporation

Building Permit
Survey no. Gut No 59 & 60
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.