01

Complete project overview

MahaRERA · Registration filing
Floors
33
Buildings
4
Parking
49 spaces
Land area
5,973 sq m
Sanctioned built-up
5,076 sq m
Recreational open space
897 sq m

Timeline

RERA registeredJun 2019
Proposed completionDec 2023
TodaySep 2026
Construction progress
Podiums0%
Water Supply0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Community Building…0%
Water conservation…0%
Energy managemcnt0%
Aggregate area of …0%
Open Parking0%
Electrical meter r…50%
Sewerage (Chamber,…70%
Internal Roads & F…92%
Fire protection an…95%
External finishes97%
OC-readiness97%
Internal finishes99%
Flat fit-out99%
Stairs & lifts99%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

SHREE SAI BALAJI ASSOCIATES

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2019–2023Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Varap
Taluka
Kalyan
District
Thane
Pincode
421301
Survey no.
S NO 40 HISSA NO 3
North boundary
S NO 40
East boundary
S NO 38 OR 4 AND S NO 39 OR 2
South boundary
S NO 40 OR 3
West boundary
S NO 40 OR 2 AND 5
What’s nearby
Schools1 school within 1km · College or university 974m away
HealthcareHospital 190m away · 5 clinics within 1km
LifestylePark 678m away
ShoppingSupermarket 1.4km away
Getting around
Expressway 20 m · Kalyan-Murbad RoadPrimary road 784 m · Agra RoadRailway line 1.9 kmRailway station 1.9km away (Kalyan Junction)Limited bus connectivity nearby
Water & environment
Water body 791 m · Kala TalaoRiver 1.5 km · Ulhas
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Sahayak Sanchalak Nagar Rachna

Building Permit
Survey no. S NO 40 HISSA NO 3

The promised possession date (30 Dec 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that approved this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

07

Other projects nearby

The register · within 25 km

2,603 residential projects still under way within 25 km. Step out ring by ring:

60 projects within 1 km — showing the nearest 6.

KalyanResidential / Group Housing

SARVODAY APEX

GURUDUTT DEVELOPER

Aug 2020registered
Jun 2026target completion
Government Guidance Rate₹65,469/sq ydScale116 flatsAuthorityMahaRERA
ChikangharOthers

TANISHQ

PHOENIX REALTY

Jan 2023registered
Dec 2026target completion
Government Guidance Rate₹63,295/sq ydScale179 flatsAuthorityMahaRERA
GandhareResidential / Group Housing

Vedant Palacia Phase IV Wing B-Brutus

THARWANI PROPERTIES

Feb 2023registered
Dec 2026target completion
Government Guidance Rate₹73,496/sq ydScale100 flatsAuthorityMahaRERA
GandhareResidential / Group Housing

Vedant Palacia Phase V Wing C-Cassius

THARWANI PROPERTIES

Jan 2024registered
Dec 2027target completion
Government Guidance Rate₹73,496/sq ydScale14 flatsAuthorityMahaRERA
ChikangharResidential / Group Housing

THE PYRAMID ONE

PYRAMID DEVELOPERS

Oct 2023registered
Sep 2026target completion
Government Guidance Rate₹63,295/sq ydScale32 flatsAuthorityMahaRERA
VarapResidential / Group Housing

KRISHNA EMPIRE 3

Jai Mata Di Construction

Apr 2024registered
Dec 2026target completion
Scale51 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.