Complete project overview

MahaRERA · Registration filing
Units
39 units
Mix
19 × 1 BHK · 11 × Office · 7 × 1 RK · 2 × Shop
Carpet area
9–33 sq mper-unit range, as filed
Floors
11
Land area
1,060 sq m
Sanctioned built-up
2,379 sq m

Timeline

RERA registeredJun 2021
Proposed completionApr 2025
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Water conservation…1%
Internal Roads & F…2%
Fire protection an…2%
Flat fit-out3%
Stairs & lifts3%
Electrical meter r…4%
Excavation5%
Basement (if any)5%
Plinth5%
External finishes8%
OC-readiness9%
Internal finishes26%
Superstructure41%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

39 units across 17 batches
TypeArea sq mCount
Office201
Shop271
Office92
1 BHK298
Office111
Office191
Office201
1 BHK339
1 RK206
Office331
Office201
1 RK201
Shop151
Office201
1 BHK252
Office211
Office251

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

KRISHNA ASSOCIATE

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
2Projects
2Cities
2019–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
82 homeson the public record across 2 projects
2,379 sq mbuilt-up filed
2,279 sq mland declared
₹43.98 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Mira Bhayandar Municipal CorporationMunicipal Corporationthis project1 of 2 projects
Vadodara Municipal CorporationMunicipal / Corporation1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
BHAYANDAR
Taluka
Thane
District
Thane
Pincode
401101
Survey no.
54/18A,18B
North boundary
12 MT WIDE D P ROAD
East boundary
AMRUT MANTHAN AND JAI SAI SAGAR BUILDING
South boundary
SHIV SHAKTI COMPLEX BUILDING
West boundary
GAYATRI BUILDING AND INTERNAL ROAD
What’s nearby
Schools1 school within 1km
HealthcareHospital 166m away · 6 clinics within 1km · Pharmacy within 1km
Lifestyle5 parks within 500m · Gym or sports centre 1.1km away
ShoppingSupermarket 1.2km away · Bank 478m away · ATM within 500m
Getting around
Expressway 4.3 km · Mumbai Delhi HighwayPrimary road 1.4 kmRailway line 402 mRailway station 478m away (Bhayandar)Bus stop within 500m
Water & environment
Water body 137 m · Khari Talao
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Mira Bhayandar Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 54/18A,18B

The promised possession date (30 Apr 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Mira Bhayandar Municipal Corporation

Municipal corporation

Has approved 127 RERA projects0.6% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
101
On record
2,811 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.