HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
42 spaces
Land area
859 sq m
Sanctioned built-up
2,745 sq m

Timeline

RERA registeredApr 2023
Proposed completionJun 2026
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Flat fit-out0%
OC-readiness0%
Landscaping & Tree…0%
Electrical meter r…18%
External finishes36%
Water Supply36%
Water conservation…42%
Storm Water Drains68%
Stairs & lifts76%
Internal finishes85%
Sewerage (Chamber,…97%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

NILESH RAMESHCHANDRA RATHI

IndividualPromoter type
Nagpur, MAHARASHTRABased in
1Projects
1City
2023–2026Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Nagpur (M Corp.)
Taluka
Nagpur (Urban)
District
Nagpur
Pincode
440010
Survey no.
PLOT NO.25, CIVIL STATION EXPANSION SCHEME, CTS NO.205, NIT KH NO.79-80, SHEET NO.(39) 17/II
North boundary
ROAD
East boundary
ROAD
South boundary
PLOT NO 15
West boundary
PLOT NO 24
What’s nearby
Schools1 school within 1km · College or university 1.0km away
HealthcareHospital 180m away · 6 clinics within 1km · Doctor's clinic within 1km
LifestylePark 1.0km away · Gym or sports centre 1.8km away · 9 restaurants and cafes within 1km
ShoppingSupermarket 243m away · Mall 1.6km away · Bank 650m away
Getting around
Expressway 832 mPrimary road 676 m · West High Court RoadRailway line 2.1 kmMetro station 360m away (Institute of Engineers)Bus stop within 1km
Water & environment
Water body 224 mRiver 235 m · Naag
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Nagpur Municipal Corporation

Municipal Corporation
Building Permit
Survey no. PLOT NO.25, CIVIL STATION EXPANSION SCHEME, CTS NO.205, NIT KH NO.79-80, SHEET NO.(39) 17/II

The promised possession date (30 Jun 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Nagpur Municipal Corporation

Municipal corporation

Has approved 150 RERA projects0.7% of Maharashtra.

an apartments market97% apartments · 3% plotted layouts. Apartments like yours are this body's core business.

Builders
126
On record
1,675 flats · 244 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.