HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
4
Parking
39 spaces
Land area
780 sq m
Sanctioned built-up
2,801 sq m

Timeline

RERA registeredJul 2025
Proposed completionDec 2028
TodayJul 2026
Construction progress
Internal finishes0%
Flat fit-out0%
Water Supply0%
Landscaping & Tree…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
OC-readiness4%
External finishes8%
Sewerage (Chamber,…20%
Stairs & lifts33%
Stilt floor50%
Superstructure50%
Excavation100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

RADHE KRISHNA DEVELOPERS

PartnershipPromoter type
Thane, MAHARASHTRABased in
8Projects
7Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
167 homes · 214 plotson the public record across 8 projects
12,437 sq mbuilt-up filed
8,533 sq mland declared
₹24.98 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 6 projects
Ahmedabad Urban Development AuthorityUrban Development Authority1 of 6 projects
BadwaniTown & Country Planning (DTCP)1 of 6 projects
City Industrial Development Corporationthis project1 of 6 projects
Nagar Rachna Aani Mulyanirdharan Vibhag1 of 6 projects
Rajkot Municipal CorporationMunicipal / Corporation1 of 6 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Dapoli
Taluka
Panvel
District
Raigarh
Pincode
410206
Survey no.
Plot number 49, sector 8, Pushpak Node, Dapoli, Panvel
North boundary
Plot No. 48
East boundary
Plot No. 55 & 56
South boundary
Plot No. 50
West boundary
11 Mtr Wide road
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.7km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 404 m · JNPT RoadPrimary road 218 m · Dapoli Targhar RoadRailway line 136 m · JNPTRailway station 3.8km away (Khandeshwar)Limited bus connectivity nearby
Water & environment
Water body 233 m · Pargaon TalaabRiver 774 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

City Industrial Development Corporation

Building Permit
Survey no. Plot number 49, sector 8, Pushpak Node, Dapoli, Panvel
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.