Complete project overview

MahaRERA · Registration filing
Floors
16
Buildings
4
Parking
47 spaces
Land area
6,380 sq m
Sanctioned built-up
5,515 sq m
Recreational open space
1,073 sq m

Timeline

RERA registeredAug 2017
Proposed completionDec 2022
TodayJul 2026
Construction progress
Podiums0%
Water Supply0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Open Parking0%
HEALTH CLUB0%
Sewerage (Chamber,…15%
OC-readiness25%
Flat fit-out50%
Stairs & lifts65%
Internal finishes95%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
External finishes100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

M/s. Arun Bhoomi Corporation

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2017–2022Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Mira-Bhayandar (M Corp.)
Taluka
Thane
District
Thane
Pincode
401107
Survey no.
1391
North boundary
140
East boundary
139
South boundary
D P ROAD
West boundary
147
What’s nearby
SchoolsNearest school 1.7km away
HealthcareHospital 334m away · 1 clinic within 1km
Lifestyle1 park within 500m · Gym or sports centre 733m away · 4 restaurants and cafes within 1km
ShoppingSupermarket 883m away · Mall 854m away · Bank 342m away
Getting around
Expressway 531 m · Western Express HighwayPrimary road 950 m · Mira Bhayandar RoadRailway line 1.8 km · Western Railway Virar to BorivaliMetro station 748m away (Miragaon)Bus stop within 1km
Water & environment
Water body 159 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Mira Bhayendra Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 1391

The promised possession date (29 Dec 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation

A city municipal corporation that sanctions projects within its own limits. It has approved 12,653 RERA projects across 34 districts about 1 in 2 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation5 cases on record, earliest 2010
Compliance23 non-compliance notices on record
Appeals3 appeals before the tribunal
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

71 complaints on MahaRERA’s register for this project 71 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.