Complete project overview

MahaRERA · Registration filing
Plots
89 plots
Land area
20,300 sq m
Recreational open space
5,989 sq m

Timeline

RERA registeredJul 2024
Proposed completionOct 2027
TodayJul 2026
Construction progress
Water Supply0%
Street Lighting0%
CLUB HOUSE BUILDIN…0%
CHILDRENS PLAY ARE…0%
Landscaping & Tree…10%
Electrical meter r…10%
Internal Roads & F…50%
Aggregate area of …70%
Storm Water Drains80%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

RAJESH sambhaji sathe

IndividualPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Jejuri (M Cl)
Taluka
Purandhar
District
Pune
Pincode
412303
Survey no.
NEW GAT NO 64P OLD GAT NO 134P and new gat no 66p old gat 135p
North boundary
adj gat
East boundary
adj gat
South boundary
adj gat
West boundary
adj gat
What’s nearby
Schools2 schools within 500m
HealthcareHospital 301m away
LifestyleNo parks within 2km · 3 restaurants and cafes within 1km
ShoppingNo supermarket within 2km
Getting around
Expressway 136 m · Pune - Pandharpur RoadPrimary road 7 m · Jejuri Morgaon Baramati RoadRailway line 1.5 kmRailway station 1.5km away (Jejuri)Limited bus connectivity nearby
Water & environment
Water body 527 m · Punyashlok Ahilyadevi Holkar TalaoRiver 3.3 km · Karha River
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Town Plannier Baramati Br Baramati

Layout Permit
Survey no. NEW GAT NO 64P OLD GAT NO 134P and new gat no 66p old gat 135p
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.