Complete project overview

MahaRERA · Registration filing
Plots
30 plots
Land area
8,100 sq m
Sanctioned built-up
4,771 sq m
Recreational open space
812 sq m

Timeline

RERA registeredFeb 2023
Proposed completionOct 2027
TodayJul 2026
Construction progress
Landscaping & Tree…95%
Sewerage (Chamber,…97%
Street Lighting97%
Internal Roads & F…98%
Water Supply100%
Storm Water Drains100%
Water conservation…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Alliance Hariom Infrastructure

PartnershipPromoter type
Nagpur, MAHARASHTRABased in
3Projects
1City
2020–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
95 plotson the public record across 3 projects
16,515 sq mplotted area
16,515 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Gotal Panjari
Taluka
Nagpur (Rural)
District
Nagpur
Pincode
441108
Survey no.
Kh no. 53/2/1 at Gotal panjri, P.H NO 38, Nagpur rural, District-Nagpur.
North boundary
ADJ KH NO - 52
East boundary
VILLAGE ROAD NO 122
South boundary
KH NO-53-2-2
West boundary
KH NO-50
What’s nearby
SchoolsNearest school 1.1km away
HealthcareNearest hospital 2.5km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.0 km · Outer Ring RoadPrimary road 3.4 km · Manish Nagar FlyoverRailway line 2.7 kmMetro station 2.8km away (New Airport)Limited bus connectivity nearby
Water & environment
Water body 3.7 km
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.