Complete project overview

MahaRERA · Registration filing
Floors
17
Buildings
2
Parking
71 spaces
Land area
1,851 sq m
Sanctioned built-up
6,638 sq m

Timeline

RERA registeredJun 2024
Proposed completionNov 2028
TodayJul 2026
Construction progress
OC-readiness0%
Storm Water Drains0%
Landscaping & Tree…0%
Community Building…0%
Energy managemcnt0%
Water conservation…18%
Flat fit-out26%
Fire protection an…36%
Water Supply44%
Electrical meter r…48%
Sewerage (Chamber,…53%
External finishes56%
Internal finishes79%
Stairs & lifts84%
Superstructure98%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

KUKREJA INFRASTRUCTURES

PartnershipPromoter type
Nagpur, MAHARASHTRABased in
8Projects
2Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
132 homeson the public record across 8 projects
1,53,452 sq mbuilt-up filed
39,468 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Nagpur Municipal Corporation (Nmc)Municipal Corporationthis project3 of 6 projects
Nagpur Municipal CorporationMunicipal Corporation2 of 6 projects
Maharashtra Airport Development Company Ltd (Madc)1 of 6 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Nagpur (M Corp.)
Taluka
Nagpur (Urban)
District
Nagpur
Pincode
440013
Survey no.
Plot No 24 and 22/B, CTS No 1861 And 1862, Sheet No 58 MOUZA JARIPATKA, NEW COLONY,
North boundary
NALLAH
East boundary
LANE
South boundary
ROAD
West boundary
PLOT NO 22-A
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 71m away · 3 clinics within 1km
LifestylePark 1.8km away · Gym or sports centre 1.3km away
ShoppingSupermarket 1.6km away · Mall 1.3km away
Getting around
Expressway 948 m · Inner Ring RoadPrimary road 1.1 km · LIC- Automotive Double Decker FlyoverRailway line 790 mMetro station 1.1km away (Indora Square)Limited bus connectivity nearby
04

Planning authority

MahaRERA · Approved building plan

Nagpur Municipal Corporation (Nmc)

Municipal Corporation
Building Permit
Survey no. Plot No 24 and 22/B, CTS No 1861 And 1862, Sheet No 58 MOUZA JARIPATKA, NEW COLONY,
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Nagpur Municipal Corporation (Nmc)

Municipal corporation

Has approved 36 RERA projects0.2% of Maharashtra.

an apartments market97% apartments · 3% plotted layouts. Apartments like yours are this body's core business.

Builders
29
On record
0 flats · 31 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.