Complete project overview

GujRERA · Registration filing
Units
129 units
Mix
129 × 8 Type of Apartment
Carpet area
186–356 sq mper-unit range, as filed
Blocks
3
Parking
399 spaces
Land area
7,466 sq m

Timeline

Project startedMar 2014
RERA registeredNov 2017
Proposed completionDec 2019
TodayJul 2026
Construction progress

94% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

129 units across 1 batch
TypeArea sq mCount
8 Type of Apartment207129

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

GujRERA · Promoter registration

Adani Township and Real Estate Company Private Limited

COMPANYPromoter type
Ahmedabad, GujaratBased in
12Projects
2Cities
2017–2021Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
800 homeson the public record across 12 projects
1,58,648 sq mland declared
₹1310.01 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

GujRERA · Registration filing
Taluka
Daskroi
District
Ahmedabad
Pincode
382423
Address
ShantigramNr.Vaishnodevi Circle, S.G.Highway,
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.4km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.0 kmPrimary road 2.0 kmRailway line 481 mRailway station 1.6km away (Khodiyar Junction)Limited bus connectivity nearby
Water & environment
Water body 23 mCanal 1.2 km · Narmada Canal
distances only — not a flood assessment
Land, title & encumbrance
Mortgage129 unit(s) mortgaged to YES BANK · ₹225.00 Cr outstanding
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹29.42 Cr declared to build 129 flats. What that works out to:

₹92.88 Lakh – ₹3.37 Crdeclared unit pricerange on the filing — not a live asking price
₹22.81 Lakhdeclared cost per flatall-in — land + construction
17%of the cost is land₹610/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

GujRERA · Approved building plan

Ahmedabad Urban Development Authority

Urban Development Authority
Building Permitapproved 7 Nov 2017 · 8 yrs ago

The promised possession date (31 Dec 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Building-Use (BU) permission — the occupancy sign-off, on record

All 3 blocks carry a Building-Use (BU) permission (latest 1 Nov 2019)— Gujarat’s legal-to-occupy sign-off, and the completion proof most RERA records simply don’t carry. Still confirm the BU covers your specific unit before you rely on it.

The approving body, at scale

Ahmedabad Urban Development Authority

Urban Development Authority

Has approved 2,400 RERA projectsabout 1 in 7 in Gujarat.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,936
On record
3,12,468 flats · 1,153 plots
Reach
22 talukas
Since
2007

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — GujRERA does not publish a complaints register. This read cannot speak to them either way.