Complete project overview

MahaRERA · Registration filing
Floors
6
Land area
123 sq m
Sanctioned built-up
383 sq m

Timeline

RERA registeredFeb 2022
Proposed completionJun 2024
TodayJul 2026
Construction progress
Podiums0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Fire protection an…0%
Electrical meter r…0%
Internal finishes50%
Basement (if any)80%
Plinth80%
Stilt floor80%
Superstructure80%
Excavation100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

LFKA BUILDERS AND DEVELOPERS

PartnershipPromoter type
Thane, MAHARASHTRABased in
6Projects
1City
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
118 homeson the public record across 6 projects
4,833 sq mbuilt-up filed
1,524 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kalyan-Dombivali (M Corp.)
Taluka
Kalyan
District
Thane
Pincode
421301
Survey no.
1682B AND 1682C
North boundary
CTS NO 1681
East boundary
CORPORATION ROAD - VARSHA MEDICAL LANE
South boundary
DR AMBEDKAR ROAD
West boundary
DR AMBEDKAR ROAD
What’s nearby
SchoolsNo schools within 2km · College or university 486m away
HealthcareHospital 16m away · 7 clinics within 1km
LifestylePark 1.3km away
ShoppingNo supermarket within 2km · Bank 449m away
Getting around
Expressway 968 m · Chatrapati Shivaji Maharaj Putala ChowkPrimary road 281 mRailway line 651 mRailway station 670m away (Kalyan Junction)Bus stop within 500m
Water & environment
Water body 817 m · Kala TalaoRiver 1.4 km · Ulhas
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.