01
Complete project overview
MahaRERA · Registration filing- Floors
- 23
- Buildings
- 2
- Parking
- 692 spaces
- Land area
- 2,223 sq m
- Sanctioned built-up
- 32 sq m
- Recreational open space
- 10,162 sq m
Timeline
RERA registeredDec 2022
Proposed completionDec 2026
TodayJul 2026
Construction progressPer-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
Podiums0%
Street Lighting0%
Aggregate area of …0%
Landscaping & Tree…50%
Community Building…60%
Flat fit-out80%
OC-readiness86%
Internal Roads & F…90%
Storm Water Drains90%
Treatment And Disp…90%
Electrical meter r…90%
Stairs & lifts98%
External finishes98%
Internal finishes99%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Water Supply100%
Sewerage (Chamber,…100%
Solid Waste Manage…100%
Water conservation…100%
Fire protection an…100%
02
Builder’s track record
MahaRERA · Promoter registrationKOLTE-PATIL KIWALE PROJECT PRIVATE LIMITED
CompanyPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2022–presentActive
Timelineevery project, start → promised completion
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
03
Location
MahaRERA · Registration filing- Village
- Kivale
- Taluka
- Mawal
- District
- Pune
- Pincode
- 412101
- Survey no.
- S NO 19 HISSA NO 1 TO 7 PLUS 9 SLASH 1
- North boundary
- PROPOSED FUTURE DEVELOPMENT OF LARGER LAND
- East boundary
- OPEN SPACE 3OF LARGER LAYOUT
- South boundary
- 12 M WIDE INTERNAL ROAD
- West boundary
- 18 M WIDE DP ROAD
What’s nearby
SchoolsNearest school 1.9km away
HealthcareHospital 754m away · 1 clinic within 1km · Pharmacy within 1km
Lifestyle1 park within 500m · 27+ restaurants and cafes within 1km
ShoppingSupermarket 257m away · Convenience store within 500m · Bank 735m away
Getting around
Expressway 151 m · Gramdaivat Shree Bapdev Maharaj FlyoverPrimary road 220 mRailway line 1.6 km · Mumbai–Pune RailwayRailway station 2.2km away (Dehu Road)Bus stop within 1km
Water & environment
River 1.4 km · Kasarsai
distances only — not a flood assessmentLegal & regulatory recordFrom MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
LitigationNone declared to MahaRERA
1 complaint on MahaRERA’s register for this project — 1 disposed.
A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.