HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
10
Buildings
2
Parking
49 spaces
Land area
800 sq m
Sanctioned built-up
2,854 sq m
Recreational open space
236 sq m

Timeline

RERA registeredAug 2025
Proposed completionMar 2029
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Open Parking0%
Excavation70%
Plinth70%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Star Realtors

PartnershipPromoter type
Mumbai City, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Others
Taluka
Ward E
District
Mumbai City
Pincode
400010
Survey no.
1/79
North boundary
d
East boundary
a
South boundary
c
West boundary
b
What’s nearby
SchoolsNearest school 1.1km away · College or university 1.6km away
HealthcareHospital 393m away · Clinic within 2km · Pharmacy within 1km
LifestylePark 1.6km away · 4 restaurants and cafes within 1km
ShoppingNo supermarket within 2km · Mall 1.3km away · Bank 362m away
Getting around
Expressway 1.1 km · Dr Babasaheb Ambedkar MargPrimary road 233 m · P D' Mello RoadRailway line 159 m · Central Railway (Harbour Line)Railway station 397m away (Dockyard Road)9 bus stops within 500m
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. 1/79
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.