3 on filequarterly progress reports filed with RERA
Timeline
RERA registeredAug 2020
Proposed completionJun 2025
TodaySep 2026
Construction progress
100% overall, as filed
Sewerage0%
Landscaping And Tree Planting0%
Street Lighting0%
Water Conservation Rain Water Harvesting0%
Energy Maanagement0%
Boundary Wall0%
Storm Water Drains10%
Water Supply20%
Internal Roads And Footpaths30%
From the builder's latest quarterly progress report filed with RERA Chhattisgarh — % complete overall and per infrastructure work, as of that filing. A dated snapshot, not a live tracker.
Find your plot
Filed by type and size, in the batches the builder registered — not a per-plot listing. Look yours up.
16 plots across 13 batches
TypeArea sq mCount
Plot1671
Plot1252
Plot1172
Plot1051
Plot1461
Plot842
Plot691
Plot1101
Plot1061
Plot1231
Plot1481
Plot1901
Plot2291
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).
Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.
Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Expressway 1.7 kmPrimary road 1.7 kmRailway line 1.6 kmRailway station 2.9km away (Raigarh)Limited bus connectivity nearby
Water & environment
Water body 583 mRiver 591 m · Kelo
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price
₹1.02 Cr declared to build 16 plots. What that works out to:
₹6.40 Lakhdeclared cost per plotall-in — land + construction
31%of the cost is land
This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Location & price analysis — done
04
Government Guidance Rate
Chhattisgarh registration department
In Chhattisgarh it’s called the collector guideline rate.
No government guidance rate is shown for this project.
Chhattisgarh's government guidance rates aren't in Horizon's record yet.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
Government Guidance Rate — done
05
Complaints & litigation
RERA Chhattisgarh · public record
Complaints, as the builder reports them
None in the builder’s latest quarterly return to RERA Chhattisgarh.
The builder’s own count of grievances it received — not RERA Chhattisgarh’s register, which isn’t published. Cases the builder declares are listed below.
What the builder declared
Declared to RERA Chhattisgarh
Litigation
None declared in this filing
Only what the builder declared, or what RERA Chhattisgarh records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with RERA Chhattisgarh, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
06
Other projects nearby
The register · within 25 km
46 plotted projects still under way within 25 km. Step out ring by ring:
Of the 103 projects the radar draws within 6 km — every kind, every stage — 42 are plotted projects still under way. This list keeps only those, and looks further out.