Complete project overview

MahaRERA · Registration filing
Floors
6
Buildings
6
Parking
199 spaces
Land area
2,123 sq m
Sanctioned built-up
2,755 sq m
Recreational open space
250 sq m

Timeline

RERA registeredMay 2022
Proposed completionMar 2032
TodayJul 2026
Construction progress
Podiums0%
Water Supply0%
Sewerage (Chamber,…0%
Landscaping & Tree…0%
Water conservation…0%
Electrical meter r…0%
Aggregate area of …0%
OC-readiness95%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

MORAYA DEVELOPERS

PartnershipPromoter type
Satara, MAHARASHTRABased in
3Projects
3Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
91 homeson the public record across 3 projects
6,269 sq mbuilt-up filed
4,942 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kodoli (CT)
Taluka
Satara
District
Satara
Pincode
415004
Survey no.
S NO 30/5/1C
North boundary
CANNEL
East boundary
S NO 30 5 1D
South boundary
ROAD
West boundary
S NO 30 5 1B AND 5 2
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.0km away · 1 clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Bank 644m away
Getting around
Expressway 1.5 kmPrimary road 215 mRailway line 3.7 kmRailway station 3.8km away (Satara)Limited bus connectivity nearby
Water & environment
Canal 603 mRiver 2.4 km · KrishnaWater body 2.9 km
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.