1 × Shop No 2, 1 × Shop No 3, 1 × Shop No 101, 1 × Shop No 1, 1 × Shop No 102, 1 × Shop No 201, 1 × Shop No 202, 1 × Shop No 301, 1 × Shop No 302, 1 × Shop No 401, 1 × Shop No 402
Saleable area
489–1235 sq mper unit, as filed
Floors
4
Land area
3,299 sq m
Built-up area
7,779 sq m
Road widening
308 sq mland set aside for road widening
Timeline
RERA approvedMar 2017
Proposed completionDec 2020
TodaySep 2026
Construction progress
90% overall, as filed
Podiums0%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.
Find your flat
Filed by floor and type and size, in the batches the builder registered — not a per-flat listing. Look yours up.
8 of 11 available
BuildingFloorTypeArea sq mAvailable
MADINAGUDA1Shop No 2mortgaged6681 of 1
MADINAGUDA1Shop No 34891 of 1
MADINAGUDA1Shop No 1011,2351 of 1
MADINAGUDA1Shop No 16180 of 1
MADINAGUDA1Shop No 1025490 of 1
MADINAGUDA2Shop No 201mortgaged1,0461 of 1
MADINAGUDA2Shop No 202mortgaged7621 of 1
MADINAGUDA3Shop No 3011,0461 of 1
MADINAGUDA3Shop No 3027620 of 1
MADINAGUDA4Shop No 4011,0461 of 1
MADINAGUDA4Shop No 4027621 of 1
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the builder declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the builder that any specific flat is released before relying on clear title.
Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.
Planning authoritiesthis builder's portfolio, by approving body
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporationthis project2 of 4 projects
Director, Town and Country PlanningTown & Country Planning (DTCP)1 of 4 projects
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authority1 of 4 projects
Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.
Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Schools2 schools within 1km · College or university 1.9km away
HealthcareHospital 218m away · Pharmacy within 500m
LifestylePark 662m away · Gym or sports centre 880m away · 9 restaurants and cafes within 1km
ShoppingSupermarket 377m away · Bank 192m away · ATM within 500m
Getting around
Expressway 867 mPrimary road 390 m · Bollaram RoadRailway line 2.5 kmMetro station 1.8km away (miyapur metro)Bus stop within 1km
Water & environment
Water body 399 m · Miyapur Cheruvu
distances only — not a flood assessment
Declared external development
Water supply100%
Sewerage (Chamber,…100%
Green Strip/TOT LO…100%
Sewage100%
Rainwater100%
Renewable energy100%
Fire safety100%
Electricity100%
Roads0%
Rainwater0%
Street lighting0%
Community Building…0%
Solid waste0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
Location — done
04
Government Guidance Rate
Telangana registration department
In Telangana it’s called the market value — the registration department's figure, not a sale price.
No government guidance rate is shown for this project.
Telangana's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
Government Guidance Rate — done
05
Planning authority
RERA Telangana · Approved building plan
Greater Hyderabad Municipal Corporation (GHMC)
Municipal / Corporation
Building Permit
Survey no. 111
The promised possession date (31 Dec 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
The occupancy certificate — the proof that isn’t here
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
The approving body, at scale
GHMC
Municipal Corporation · Hyderabad city core
Has approved 3,102 RERA projects — about 1 in 4 in Telangana.
an apartments market — 99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.
Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016
More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.