MAJESTIQUE MARBELLA PHASE IV

P52100031184 · MahaRERA · https://gethorizon.in/projects/majestique-marbella-phase-iv-kharadi-pune-rftjbq69

Registration lapsed

This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Units
93 units
Mix
48 × 3 BHK · 45 × 2 BHK
Carpet area
64–85 sq mper-unit range, as filed
Floors
20
Parking
96 spaces
Land area
2,351 sq m
Sanctioned built-up
7,464 sq m
Recreational open space
1,736 sq m

Timeline

RERA registeredOct 2021
Proposed completionDec 2025
TodaySep 2026

Find your flat

Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.

93 units across 2 batches
TypeArea sq mCount
2 BHK6445
3 BHK8548

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Builder registration

Majestique Empire LLP

PartnershipPromoter type
Pune, MAHARASHTRABased in
6Projects
1Cities
2020–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
610 homeson the public record across 6 projects
48,700 sq mbuilt-up filed
15,034 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Pune Municipal CorporationMunicipal Corporationthis project5 of 6 projects
Pune Municipal Corporation PuneMunicipal Corporation1 of 6 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from Majestique Empire LLP— the full portfolio →

03

Location

MahaRERA · Registration filing
District
Pune
Pincode
411014
Survey no.
SURVEY NO 42/1 AND SURVEY NO 42/2/2
North boundary
ADJ PLOT S NO 42 PART
East boundary
ADJ PLOT S NO 42 PART
South boundary
9 M WIDE INTERNAL ROAD
West boundary
18 M WIDE DP ROAD
What’s nearby
Schools1 school within 500m · College or university 1.5km away · Library 854m away
HealthcareHospital 732m away · 5 clinics within 1km · Pharmacy within 500m
LifestylePark 1.4km away · 20+ restaurants and cafes within 1km
ShoppingSupermarket 730m away · Mall 1.2km away · Convenience store within 500m
Getting around
Expressway 1.1 km · Kharadi BypassPrimary road 2.7 km · Mundhwa RoadRailway line 3.4 km · Pune - Daund Railway LineRailway station 3.5km away (Ramwadi Station)Limited bus connectivity nearbyAirport 4.5km away
Water & environment
River 987 m · Mula-Mutha
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Pune Municipal Corporation

Municipal Corporation
Building Permit
Survey no. SURVEY NO 42/1 AND SURVEY NO 42/2/2

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Pune Municipal Corporation

Municipal corporation

Has approved 1,863 RERA projectsabout 1 in 11 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,351
On record
9,749 flats · 439 plots
Reach
3 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

3,021 residential projects still under way within 25 km. Step out ring by ring:

16 projects within 1 km — showing the nearest 6.

KharadiResidential / Group Housing

SHUBH SHAGUN

Shubh Housing

Nov 2018registered
Dec 2026target completion
Scale327 flatsAuthorityMahaRERA
KHARADIResidential / Group Housing

MAJESTIQUE MARBELLA PHASE 1

Majestique Empire LLP

Jul 2020registered
Jun 2026target completion
Scale177 flatsAuthorityMahaRERA
KHARADIResidential / Group Housing

MAJESTIQUE MARBELLA PHASE V

Majestique Empire LLP

Jan 2022registered
Dec 2026target completion
Scale157 flatsAuthorityMahaRERA
KharadiOthers

Palladio Kharadi Central Phase 2

Vilas Javdekar Eco Homes

Oct 2024registered
Dec 2028target completion
1 open complaintScale377 flatsAuthorityMahaRERA
PuneOthers

Raichandani Aura

Raichandani Constructions Private Limited

Jan 2025registered
Aug 2028target completion
Scale90 flatsAuthorityMahaRERA
PuneResidential / Group Housing

ANANDI

SAI DEVELOPERS

Feb 2025registered
Dec 2029target completion
Government Guidance Rate₹70,051/sq ydScale53 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.