Complete project overview

MahaRERA · Registration filing
Floors
19
Buildings
2
Parking
79 spaces
Land area
2,919 sq m
Sanctioned built-up
4,343 sq m

Timeline

RERA registeredAug 2017
Proposed completionDec 2026
TodayJul 2026
Construction progress
OC-readiness80%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
Sewerage (Chamber,…100%
Landscaping & Tree…100%
Water conservation…100%
Fire protection an…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Pruthvi Builders & Developers

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2017–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kalamboli
Taluka
Panvel
District
Raigarh
Pincode
410218
Survey no.
Plot No.52, Sector-17
North boundary
30 mts Wide Link Road
East boundary
30 mts wide Road
South boundary
Plot No 53
West boundary
Plot No 51
What’s nearby
SchoolsNearest school 1.4km away
HealthcareHospital 574m away · 2 clinics within 1km · Pharmacy within 500m
LifestyleNo parks within 2km · Gym or sports centre 121m away · 49+ restaurants and cafes within 1km
ShoppingSupermarket 148m away · Bank 62m away · ATM within 500m
Getting around
Expressway 2.9 kmPrimary road 1.1 km · Gulmohar RoadRailway line 1.8 km · Central Railway (Harbour Line)Railway station 1.9km away (Vile Parle)9 bus stops within 500m
Water & environment
Water body 420 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Cido

Building Permit
Survey no. Plot No.52, Sector-17
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
Appeals1 appeal before the tribunal
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.