Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
10
Land area
1,162 sq m
Sanctioned built-up
2,476 sq m

Timeline

RERA registeredFeb 2023
Proposed completionJun 2024
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Stilt floor0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Water Supply90%
OC-readiness95%
Excavation100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

YUVRAJ JAYSINGRAO PATIL

IndividualPromoter type
Kolhapur, MAHARASHTRABased in
2Projects
1City
2017–2024Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
13 homeson the public record across 2 projects
3,026 sq mbuilt-up filed
1,712 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Sangli Miraj Kupwad (M Corp.)
Taluka
Miraj
District
Sangli
Pincode
416436
Survey no.
S.NO. 176/A/2/C/A, PLOT NO. 2
North boundary
ROAD
East boundary
ROAD
South boundary
PLOT NO 1
West boundary
S NO 224D
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.2km away · Clinic within 2km
LifestylePark 1.4km away
ShoppingNo supermarket within 2km · Bank 794m away
Getting around
Expressway 2.6 km · Sangli-Miraj RoadPrimary road 240 m · Kupwad MIDC RoadRailway line 2.3 kmRailway station 2.1km away (Vishrambag)Bus stop within 1km
Water & environment
Water body 616 m · Water Purification Plant
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Sangli Miraj Kupwad Corporation

Building Permit
Survey no. S.NO. 176/A/2/C/A, PLOT NO. 2

The promised possession date (1 Jun 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Sangli Miraj Kupwad Corporation

Planning authority

Has approved 32 RERA projects0.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
30
On record
0 flats · 0 plots
Since
2021

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.