HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
12 units
Mix
9 × 4BHK · 3 × 3BHK
Booked
12 of 12 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
726 sq m
Floor area
3,486 sq m
Description
MANSIONS SKYLUXE

Timeline

Project startedAug 2017
RERA registeredJul 2021
Proposed completionJan 2022
TodayJul 2026
Construction progress

81% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings75%
Electrical Fittings75%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings80%
Installation of lifts, water pumps etc90%
Fire Fighting Fittings and Equipment90%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc90%
The external plumbing and external plastering95%
Completion of terraces floor each building95%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

0 of 12 available
TypeArea sq mAvailable
3BHK1230 of 2
3BHK1150 of 1
4BHK1700 of 1
4BHK1730 of 8

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

MANSIONS

PartnershipPromoter type
Thiruvananthapuram, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
5Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
119 homeson the public record across 5 projects
21,766 sq mbuilt-up filed
5,746 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thiruvananthapuram Municipal CorporationMunicipal Corporationthis project2 of 5 projects
Cochin Municipal CorporationMunicipal Corporation1 of 5 projects
Thiruvananthapuram MunicipalcorporationLocal body (LSGI)1 of 5 projects
Trivandrum Municipal CorporationMunicipal Corporation1 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
Golflinks
Village
SASTHAMANGALAM
Taluk
THIRUVANANTHAPRUAM
District
Thiruvananthapuram
Pincode
695003
Survey no.
33,33-1
Patta no.
16983
What’s nearby
SchoolsNearest school 1.1km away · 4 educational institutions within 1km · College or university 1.2km away
HealthcareHospital 548m away · 4 clinics within 1km
Lifestyle3 parks within 500m · Gym or sports centre 913m away · 16+ restaurants and cafes within 1km
ShoppingSupermarket 465m away · Mall 94m away · Bank 561m away
Getting around
Primary road 1.2 km · Thiruvanathapuram - Thenmala RoadRailway line 3.8 kmRailway station 4.1km away (Thiruvananthapuram Central)4 bus stops within 500m
Water & environment
Water body 119 mRiver 328 m · Killi
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Thiruvananthapuram Municipal Corporation

Municipal Corporation
approved 16 Dec 2019 · 6 yrs ago
Building Permit no. E5/73815/19Survey no. 33,33-1

The promised possession date (30 Jan 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan E5/73815/19 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Thiruvananthapuram Municipal Corporation

Municipal corporation / municipality

Has approved 224 RERA projectsabout 1 in 7 in Kerala, more than any other body in the state.

an apartments market91% apartments · 9% plotted layouts. Apartments like yours are this body's core business.

Builders
90
On record
12,045 flats · 635 plots
Since
2021

More apartment-heavy than Kerala overall — 91% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.