HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
28
Buildings
8
Parking
4 spaces
Land area
19,999 sq m
Sanctioned built-up
52,121 sq m
Recreational open space
2,025 sq m

Timeline

RERA registeredJun 2024
Proposed completionDec 2029
TodayJul 2026
Construction progress
Basement (if any)0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Excavation100%
Podiums100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Superb Maa Developers LLP

PartnershipPromoter type
Mumbai City, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Ashte
Taluka
Panvel
District
Raigarh
Pincode
410206
Survey no.
136, 138/1, 140/8/A and 140/9
North boundary
S No 140 by 2
East boundary
Prop 30 m wide DP Road
South boundary
S No 138 Part
West boundary
Existing Village Road
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 4.0km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.4 km · Old Mumbai Pune HighwayPrimary road 531 mRailway line 789 mRailway station 1.1km away (Somatne)Limited bus connectivity nearby
Water & environment
River 452 mWater body 1.8 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Maharashtra State Road Development Corporation

Building Permit
Survey no. 136, 138/1, 140/8/A and 140/9
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Maharashtra State Road Development Corporation

Planning authority

Has approved 32 RERA projects0.2% of Maharashtra.

an apartments market75% apartments · 25% plotted layouts. Apartments like yours are this body's core business.

Builders
22
On record
161 flats · 1,218 plots
Reach
3 districts
Since
2017

More layout-heavy than Maharashtra overall — 25% plots here vs 5% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.