Complete project overview

MahaRERA · Registration filing
Floors
23
Buildings
2
Parking
112 spaces
Land area
1,232 sq m
Sanctioned built-up
1,205 sq m

Timeline

RERA registeredJan 2023
Proposed completionOct 2026
TodayJul 2026
Construction progress
Podiums0%
Water Supply0%
Flat fit-out50%
OC-readiness50%
Electrical meter r…75%
Fire protection an…80%
Superstructure95%
Internal finishes95%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Stairs & lifts100%
External finishes100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Water conservation…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SHREEJI REALTORS

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
7Projects
6Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
577 homeson the public record across 7 projects
26,640 sq mbuilt-up filed
22,896 sq mland declared
₹54.92 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ambernath Municipal CouncilMunicipal Council1 of 4 projects
Municipal Corporation of Greater MumbaiMunicipal Corporationthis project1 of 4 projects
Rajkot Urban Development AuthorityUrban Development Authority1 of 4 projects
Vadodara Municipal CorporationMunicipal / Corporation1 of 4 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Taluka
Kurla
District
Mumbai Suburban
Pincode
400083
Survey no.
40A
North boundary
PLOT BEARING CTS NO 38
East boundary
30 MTR WIDE L B S ROAD
South boundary
PLOT BEARING CTS NO 41
West boundary
PLOT BEARING CTS NO 35
What’s nearby
SchoolsNearest school 1.2km away · Library 1.7km away
HealthcareHospital 146m away · 3 clinics within 1km · Doctor's clinic within 1km
LifestylePark 1.6km away
ShoppingSupermarket 1.1km away · Mall 1.2km away · Bank 21m away
Getting around
Expressway 758 m · Vikhroli FlyoverPrimary road 26 m · Lal Bahadur Shastri MargRailway line 294 m · Central Railways Fast LineRailway station 321m away (Vikhroli)13 bus stops within 500m
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. 40A
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.