Complete project overview

MahaRERA · Registration filing
Floors
32
Buildings
4
Parking
387 spaces
Land area
8,937 sq m
Sanctioned built-up
32,466 sq m

Timeline

RERA registeredAug 2017
Proposed completionDec 2024
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

West Pioneer Properties India Pvt Ltd

CompanyPromoter type
Mumbai City, MAHARASHTRABased in
1Projects
1City
2017–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
NETIVALI
Taluka
Kalyan
District
Thane
Pincode
421306
Survey no.
CS No 2 part and 421 part Tikka No 2 to 5
North boundary
Metro Residency
East boundary
S No 13 part and 17 part
South boundary
Kalyan shil road
West boundary
Metro Plaza
What’s nearby
SchoolsNo schools within 2km · College or university 2.0km away
HealthcareHospital 190m away · Clinic within 2km
LifestylePark 1.4km away
ShoppingSupermarket 2.0km away
Getting around
Expressway 2.1 kmPrimary road 138 m · Kalyan-Shil RoadRailway line 477 mRailway station 1.3km away (Kalyan Junction)Limited bus connectivity nearby
Water & environment
Water body 2.1 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Kalyan Dombivli Municipal Corporation

Municipal Corporation
Building Permit
Survey no. CS No 2 part and 421 part Tikka No 2 to 5

The promised possession date (30 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Kalyan Dombivli Municipal Corporation

Municipal corporation

Has approved 742 RERA projects3.7% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
585
On record
5,683 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation1 case on record, earliest 2011
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.