HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Plots
14 plots
Mix
14 × Bangalow / Villas
Booked
14 of 14 filed sold/bookedas declared in the RERA filing
Buildings
15
Land area
10,578 sq m
Floor area
5,527 sq m
Description
MEXICAN BUNGALOWS -PHASE1

Timeline

RERA registeredMay 2024
Proposed completionAug 2026
TodayJul 2026
Construction progress

39% overall, as filed

Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation0%
Basement(s) and Plinth0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Overhead and Underground Water Tanks.0%
Installation of lifts, water pumps etc0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings10%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc20%
Completion of terraces floor each building20%
Installation of lifts, water pumps etc20%
Sanitary Fittings20%
Electrical Fittings20%
Staircases, Lifts Wells20%
The external plumbing and external plastering20%
Overhead and Underground Water Tanks.20%
Installation of lifts, water pumps etc20%
Electrical Fittings30%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings30%
Staircases, Lifts Wells30%
Slabs of Super Structure50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
Electrical Fittings50%
Overhead and Underground Water Tanks.50%
Installation of lifts, water pumps etc50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Slabs of Super Structure50%
Sanitary Fittings50%
Electrical Fittings50%
Staircases, Lifts Wells50%
Completion of terraces floor each building50%
Sanitary Fittings50%
Electrical Fittings50%
The external plumbing and external plastering50%
Sanitary Fittings70%
Sanitary Fittings70%
Overhead and Underground Water Tanks.70%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings70%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings80%
Staircases, Lifts Wells80%
Completion of terraces floor each building80%
Completion of terraces floor each building80%
Sanitary Fittings90%
Electrical Fittings90%
Staircases, Lifts Wells90%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings95%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings99%
Excavation100%
Basement(s) and Plinth100%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Excavation100%
Basement(s) and Plinth100%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

0 of 14 available
TypeArea sq mAvailable
Bangalow / Villas3470 of 1
Bangalow / Villas2520 of 5
Bangalow / Villas3380 of 1
Bangalow / Villas3400 of 1
Bangalow / Villas3210 of 1
Bangalow / Villas3170 of 1
Bangalow / Villas2810 of 1
Bangalow / Villas2980 of 1
Bangalow / Villas2520 of 2

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

GREENTECH BUILDERS

PartnershipPromoter type
Ernakulam, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
4Projects
1Cities
2024–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
88 plotson the public record across 4 projects
42,475 sq mplotted area
42,475 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
vembilly
Village
KUNNATHUNAD
Taluk
Kunnathunad
District
Ernakulam
Pincode
683565
Survey no.
189/1-2, 189/1-3,189/1-4
Patta no.
15069, 4308,12230,11055
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.1km away
LifestyleNo parks within 2km · Gym or sports centre 957m away · 5 restaurants and cafes within 1km
ShoppingSupermarket 1.2km away · Mall 1.1km away · Bank 836m away
Getting around
Primary road 559 m · Ernakulam - Thekkady RoadNo metro or railway within 5kmBus stop within 1km
Water & environment
Canal 302 mWater body 366 m · EtekkattuchiraRiver 1.7 km
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Kunnathunadu Grama Panchayat

Grama Panchayat
approved 19 Jun 2023 · 3 yrs ago
Layout Permit no. A2-BA(214272)/2023Survey no. 189/1-2, 189/1-3,189/1-4
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan A2-BA(214272)/2023 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Kunnathunadu Grama Panchayat

Grama panchayat

Has approved 9 RERA projects0.6% of Kerala.

a plotted-layout market22% apartments · 78% plotted layouts. Your plotted layout is this body's core business.

Builders
4
On record
77 flats · 183 plots
Since
2021

More layout-heavy than Kerala overall — 78% plots here vs 19% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.