Complete project overview

MahaRERA · Registration filing
Floors
42
Buildings
6
Parking
882 spaces
Land area
7,908 sq m
Sanctioned built-up
62,319 sq m

Timeline

RERA registeredAug 2017
Proposed completionDec 2023
TodayJul 2026
Construction progress
Landscaping & Tree…0%
Open Parking10%
Energy managemcnt40%
Internal Roads & F…50%
Fire protection an…75%
Electrical meter r…80%
Sewerage (Chamber,…90%
Storm Water Drains90%
Solid Waste Manage…90%
Flat fit-out95%
External finishes95%
OC-readiness95%
Stairs & lifts99%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Water Supply100%
Treatment And Disp…100%
Water conservation…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Lokhandwala Kataria Construction Private Limited

CompanyPromoter type
Mumbai City, MAHARASHTRABased in
1Projects
1City
2017–2023Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Lower Parel
Taluka
Ward GSouth
District
Mumbai City
Pincode
400011
Survey no.
C.S.NO 1PT, 2PT
North boundary
J R BORICHA MARG
East boundary
APOLLO MILL
South boundary
REHAB BUILDINGS
West boundary
J R BORICHA MARG
What’s nearby
Schools1 school within 500m · 4 educational institutions within 1km · College or university 369m away
HealthcareHospital 236m away · 6 clinics within 1km · Doctor's clinic within 1km
LifestylePark 1.4km away · 16+ restaurants and cafes within 1km
ShoppingSupermarket 877m away
Getting around
Expressway 689 m · Dr Babasaheb Ambedkar MargPrimary road 602 m · Dr E Moses Marg FlyoverRailway line 190 mRailway station 392m away (Chinchpokli)4 bus stops within 500m
Water & environment
Water body 1.1 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Slum Rehabilitation Authority

Slum Rehabilitation Authority
Building Permit
Survey no. C.S.NO 1PT, 2PT

The promised possession date (30 Dec 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Slum Rehabilitation Authority

Planning authority

Has approved 729 RERA projects3.6% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
554
On record
15,389 flats · 0 plots
Reach
4 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation3 cases on record, earliest 2016
EncumbranceDeclared financial encumbrance on the project
Compliance8 non-compliance notices on record
Appeals20 appeals before the tribunal
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

53 complaints on MahaRERA’s register for this project 46 disposed, 7 still open.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.