HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
10
Buildings
6
Parking
50 spaces
Land area
7,310 sq m
Recreational open space
7,310 sq m

Timeline

RERA registeredSep 2019
Proposed completionAug 2025
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Treatment And Disp…0%
Solid Waste Manage…0%
Electrical meter r…0%
Aggregate area of …0%
Open Parking0%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

NAVAL RAMBAHADUR SINGH

IndividualPromoter type
Palghar, MAHARASHTRABased in
2Projects
1City
2017–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
51 homeson the public record across 2 projects
1,856 sq mbuilt-up filed
9,166 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kapase
Taluka
Palghar
District
Palghar
Pincode
401102
Survey no.
SURVEY NO 66 HISSA N 2
North boundary
ADJ G NO 67
East boundary
9 M WIDE ROAD
South boundary
LAYOUT ROAD
West boundary
AD G NO 78
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.5km away
LifestylePark 1.2km away
ShoppingNo supermarket within 2km
Getting around
Primary road 1.2 kmRailway line 912 m · Mumbai - Delhi RailwayRailway station 1.7km away (Saphale)Limited bus connectivity nearby
Water & environment
Water body 244 mRiver 4.5 km · Taki
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

District Collector Office Palghar

Collector office
Building Permit
Survey no. SURVEY NO 66 HISSA N 2

The promised possession date (20 Aug 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.