HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Plots
107 plots
Land area
14,011 sq m
Recreational open space
1,924 sq m

Timeline

RERA registeredJan 2025
Proposed completionDec 2029
TodayJul 2026
Construction progress
Landscaping & Tree…55%
Water Supply65%
Water conservation…65%
Storm Water Drains69%
Internal Roads & F…75%
Aggregate area of …75%
Sewerage (Chamber,…85%
Electrical meter r…88%
Street Lighting89%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

PRASANNA PLANNERS

PartnershipPromoter type
Nagpur, MAHARASHTRABased in
2Projects
2Cities
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2,385 plotson the public record across 2 projects
46,607 sq mplotted area
46,607 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Wanadongri
Taluka
Hingna
District
Nagpur
Pincode
441110
Survey no.
KHASRA NO. 104/21, 104/22, 104/23, 104/24, 104/25, 104/26, 104/27, 104/28, 104/37, 104/38, 104/39, 104/40, 104/41, 104/42, 104/44, MOUZA-WANADONGARI
North boundary
KH NO 103 and 15 M WIDE ROAD
East boundary
KH NO 104-29-31-32-33-34-35-36 and 12 M WIDE ROAD
South boundary
KH NO 115 and NALLAH
West boundary
KH NO 113 105 106
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Railway line 4.0 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 547 mWater body 2.9 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Council Wanadongri

Municipal Council
Layout Permit
Survey no. KHASRA NO. 104/21, 104/22, 104/23, 104/24, 104/25, 104/26, 104/27, 104/28, 104/37, 104/38, 104/39, 104/40, 104/41, 104/42, 104/44, MOUZA-WANADONGARI
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation

A city municipal corporation that sanctions projects within its own limits. It has approved 12,653 RERA projects across 34 districts about 1 in 2 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.