HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
7
Buildings
4
Parking
83 spaces
Land area
3,650 sq m
Sanctioned built-up
6,646 sq m
Recreational open space
366 sq m

Timeline

RERA registeredJun 2023
Proposed completionMar 2027
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
OC-readiness0%
Water conservation…0%
Aggregate area of …0%
Street Lighting50%
Internal Roads & F…60%
Landscaping & Tree…60%
Sewerage (Chamber,…70%
Flat fit-out80%
Excavation100%
Basement (if any)100%
Plinth100%
Superstructure100%
Internal finishes100%
Stairs & lifts100%
External finishes100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SAMEERALI RAMZANALI MOTI

IndividualPromoter type
Aurangabad, MAHARASHTRABased in
1Projects
1City
2023–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Aurangabad (M Corp.)
Taluka
Aurangabad
District
Aurangabad
Pincode
431002
Survey no.
GUT NO. 63/P, PADEGAON, AURANGABAD - 431002
North boundary
REMAINING LAND OF GUT NO 63
East boundary
7 AND HALF MTR ROAD AND LAND OF MR AKBAR MOTI
South boundary
15 METER WIDE DP ROAD
West boundary
DRAINAGE SYSTEM - NALA
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.8km away
LifestylePark 1.8km away
ShoppingNo supermarket within 2km
Getting around
Expressway 121 m · Beed ChalisgaonRailway line 1.1 kmRailway station 2.5km away (Daulatabad)Bus stop within 1km
Water & environment
Water body 3.2 km · Hathi Houz
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Aurangabad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. GUT NO. 63/P, PADEGAON, AURANGABAD - 431002
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Aurangabad Municipal Corporation

Municipal corporation

Has approved 54 RERA projects0.3% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
53
On record
324 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.