Complete project overview

MahaRERA · Registration filing
Floors
13
Buildings
4
Parking
158 spaces
Land area
3,990 sq m
Sanctioned built-up
15,951 sq m

Timeline

RERA registeredMar 2023
Proposed completionMar 2028
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Flat fit-out0%
Water Supply0%
Landscaping & Tree…0%
Street Lighting0%
Solid Waste Manage…0%
Electrical meter r…0%
OC-readiness10%
Internal Roads & F…10%
Storm Water Drains10%
Water conservation…10%
Fire protection an…20%
Sewerage (Chamber,…30%
External finishes55%
Stairs & lifts60%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

MUKUNDAN INFRA

PartnershipPromoter type
Palghar, MAHARASHTRABased in
1Projects
1City
2023–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Vasai-Virar City (M Corp)
Taluka
Vasai
District
Palghar
Pincode
401203
Survey no.
132(A)
North boundary
SBI COLONY
East boundary
BHAGIRATHI BLDG
South boundary
KRISHNA APARTMENT
West boundary
OPEN PLOT
What’s nearby
SchoolsNearest school 1.7km away
HealthcareHospital 1.2km away · Clinic within 2km
LifestylePark 1.0km away
ShoppingSupermarket 1.4km away
Getting around
Expressway 1.1 km · Shahid Major Kaustubh Rane flyoverPrimary road 1.1 km · Mathuradas Vasanji Road (Andheri Kurla Road)Railway line 2.1 kmMetro station 1.9km away (CSMI Airport International T2)Limited bus connectivity nearby
Water & environment
Water body 840 mRiver 875 m · Mithi River
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Vasai Virar City Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 132(A)
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Vasai Virar City Municipal Corporation

Municipal corporation

Has approved 627 RERA projects3.1% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
513
On record
8,010 flats · 60 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.