HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
26
Buildings
8
Parking
87 spaces
Land area
16,160 sq m
Sanctioned built-up
19,179 sq m

Timeline

RERA registeredJan 2023
Proposed completionDec 2026
TodayJul 2026
Construction progress
Podiums0%
Storm Water Drains0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Water Supply35%
Landscaping & Tree…40%
Sewerage (Chamber,…50%
OC-readiness60%
Flat fit-out86%
Internal finishes90%
External finishes92%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Stairs & lifts100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

JSB HOMEMAKERS PVT LTD

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
2Projects
1City
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2 projectson the public record across 2 projects
31,134 sq mbuilt-up filed
24,395 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Vasai-Virar City (M Corp)
Taluka
Vasai
District
Palghar
Pincode
401208
Survey no.
Survey No. 73, Survey No. 75 Hissa No. 2/1, Survey No. 75 Hissa 3, Survey No. 82 Hissa No. 5, Survey No. 84 Hissa No. 7, Survey No. 84 Hissa No. 10
North boundary
Emonics Tower
East boundary
30M Road
South boundary
20 M Road
West boundary
Building No 2 Wing D
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.2km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 3.6 km · Mumbai Delhi HighwayPrimary road 845 m · Vasai RoadRailway line 2.0 kmRailway station 2.1km away (Vasai Road)Bus stop within 1km
Water & environment
Water body 222 mRiver 398 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Vasai Virar City Municipal Corporation

Municipal Corporation
Building Permit
Survey no. Survey No. 73, Survey No. 75 Hissa No. 2/1, Survey No. 75 Hissa 3, Survey No. 82 Hissa No. 5, Survey No. 84 Hissa No. 7, Survey No. 84 Hissa No. 10
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Vasai Virar City Municipal Corporation

Municipal corporation

Has approved 627 RERA projects3.1% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
513
On record
8,010 flats · 60 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.