HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
17
Buildings
2
Parking
85 spaces
Land area
2,352 sq m
Sanctioned built-up
4,102 sq m
Recreational open space
239 sq m

Timeline

RERA registeredJan 2025
Proposed completionDec 2029
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Stilt floor0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Street Lighting0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Superstructure23%
Excavation100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Chirag Associates

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
BHAYANDAR
Taluka
Thane
District
Thane
Pincode
401101
Survey no.
old survey no 566/1B,565/3,new survey no219/1B, 220/3
North boundary
RG3
East boundary
Bunglow No 1 2 3
South boundary
Building No 1
West boundary
Building No 2
What’s nearby
SchoolsNearest school 1.2km away
HealthcareHospital 306m away · Clinic within 2km · Doctor's clinic within 1km
LifestylePark 976m away · Gym or sports centre 1.0km away
ShoppingSupermarket 711m away
Getting around
Expressway 3.7 km · Western Express HighwayPrimary road 995 mRailway line 454 m · Western Railway Virar to BorivaliMetro station 551m away (Shahid Bhagat Singh Garden)Limited bus connectivity nearby
Water & environment
Water body 340 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Mira Bhayandar Municipal Cooperation

Building Permit
Survey no. old survey no 566/1B,565/3,new survey no219/1B, 220/3
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.