Complete project overview

MahaRERA · Registration filing
Floors
25
Buildings
4
Parking
70 spaces
Land area
4,400 sq m
Sanctioned built-up
20,676 sq m
Recreational open space
2,892 sq m

Timeline

RERA registeredMar 2022
Proposed completionJun 2026
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
External finishes0%
OC-readiness0%
Internal finishes17%
Flat fit-out17%
Stairs & lifts17%
Superstructure83%
Excavation100%
Basement (if any)100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

NAVKAR ESTATE AND HOMES PVT LTD

CompanyPromoter type
Palghar, MAHARASHTRABased in
12Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
628 homeson the public record across 12 projects
67,896 sq mbuilt-up filed
52,280 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Vasai Virar City Municipal CorporationMunicipal Corporation5 of 7 projects
Laxman Bhikaji Khedkarthis project2 of 7 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Vasai-Virar City (M Corp)
Taluka
Vasai
District
Palghar
Pincode
401208
Survey no.
Survey No. 332/1,3,4,6A,7,8 & Survey No. 333/1, 2
North boundary
Survey no 335 and 350
East boundary
40 mtr wide road
South boundary
20 mtr wide road
West boundary
Survey no 335 1 2
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.8km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 4.1 kmPrimary road 624 m · Juchandra Road Sane Guruji MargRailway line 912 mRailway station 1.3km away (Naigaon)Limited bus connectivity nearby
Water & environment
River 872 m · Sopara CreekWater body 1.7 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Laxman Bhikaji Khedkar

Building Permit
Survey no. Survey No. 332/1,3,4,6A,7,8 & Survey No. 333/1, 2

The promised possession date (30 Jun 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Laxman Bhikaji Khedkar

Planning authority

Has approved 6 RERA projects0% of Maharashtra.

a mixed market67% apartments · 33% plotted layouts.

Builders
3
On record
0 flats · 46 plots
Since
2017

More layout-heavy than Maharashtra overall — 33% plots here vs 5% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.