NEELA RESIDENCY

PRM/KA/RERA/1259/410/PR/171125/000491 · RERA Karnataka · https://gethorizon.in/projects/neela-residency-dharwad-4qu5rsmx

01

Complete project overview

RERA Karnataka · Registration filing
Project name
NEELA RESIDENCY
Land area
696 sq m
Covered area
435 sq m
Open area
260 sq m

Timeline

Project startedAug 2015
Proposed completionMar 2018
RERA registeredNov 2025
TodaySep 2026
02

Builder’s track record

RERA Karnataka · Builder registration

SHREE VIJAYALAXMI BUILDERS PVT. LTD.

Mumbai SuburbanBased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Dharwad
District
Mumbai City
Pincode
400016
Address
BEHIND KALLUR PETROL PUMP KALLUR LAYOUT (GANESH PARK), HOSUR UNKAL ROAD HUBLI
What’s nearby
Schools2 schools within 1km · 10 educational institutions within 1km · College or university 80m away
HealthcareHospital 90m away · 2 clinics within 1km · Pharmacy within 500m
LifestyleNo parks within 2km · 17+ restaurants and cafes within 1km · Swimming pool within 2km
ShoppingNo supermarket within 2km · Bank 45m away · ATM within 500m
Getting around
Expressway 2.1 km · Karwar RoadPrimary road 11 m · Pune Bangalore RoadRailway line 594 mRailway station 1.1km away (Unkal)2 bus stops within 500m
Water & environment
Water body 1.9 km · Santhosh Nagar Lake
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹4.40 Cr declared. What that works out to:

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Karnataka registration department

In Karnataka it’s called the guidance value.

No government guidance rate is shown for this project.

Karnataka's guidance-value gazettes are in Horizon's record, but this project's address doesn't name a place any of its sub-registrar's tables print.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

RERA Karnataka · Approved building plan

Hubballi Dharwad Municipal Corporation

Municipal / Corporation
Building Permit

The promised possession date (31 Mar 2018) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Hubballi Dharwad Municipal Corporation

Municipal Corporation

Has approved 114 RERA projects1.3% of Karnataka.

an apartments market90% apartments · 10% plotted layouts. Apartments like yours are this body's core business.

Builders
91
On record
3,602 flats · 463 plots
Reach
5 taluks
Since
2017

More apartment-heavy than Karnataka overall — 90% apartments here vs 62% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by RERA Karnataka

07

Other projects nearby

The register · within 25 km

63 residential projects still under way within 25 km. Step out ring by ring:

4 projects within 1 km — showing the nearest 4.

DharwadApartment

D&G Homes

D AND G INFRA

Jan 2023started
Dec 2027target completion
Declared cost₹17.13 CrScale54 flatsAuthorityRERA Karnataka
HubballiApartment

Bilva Residency

Mahesh Basanna

Sep 2024started
Aug 2027target completion
Declared cost₹4.82 CrScale12 flatsAuthorityRERA Karnataka
BelagaviResidential/Group Housing

Construction of 400 @ Savadatti

KARNATAKA SLUM DEVELOPMENT BOARD

Oct 2021started
Oct 2026target completion
no escrow declaredDeclared cost₹27.20 LakhAuthorityRERA Karnataka
DharwadApartment

Pacific Vihar

PACIFIC PROPERTIES

Mar 2026started
Mar 2030target completion
Declared cost₹8.05 CrScale20 flatsAuthorityRERA Karnataka

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.