HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
48 spaces
Land area
536 sq m
Sanctioned built-up
1,817 sq m

Timeline

RERA registeredJul 2025
Proposed completionAug 2027
TodayJul 2026
Construction progress
Water Supply0%
Sewerage (Chamber,…0%
Landscaping & Tree…0%
Street Lighting0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Basement (if any)50%
Excavation100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

M/s. Shree Gurudatta Developer

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kalyan-Dombivali (M Corp.)
Taluka
Kalyan
District
Thane
Pincode
421202
Survey no.
CTS No.2426, 2427 & 2428 Mauje- Dombivali, Dombivali (West).
North boundary
Open Plot of Mr. Ravi Mhatre
East boundary
Mayur Sahanivas CHS Ltd.
South boundary
Sumitra Niwas (Old)
West boundary
18 mtr. Road
What’s nearby
Schools2 schools within 500m
HealthcareHospital 197m away · 8 clinics within 1km · Doctor's clinic within 1km
Lifestyle2 parks within 500m · Gym or sports centre 1.9km away · 7 restaurants and cafes within 1km
ShoppingSupermarket 240m away · Convenience store within 1km
Getting around
Expressway 3.9 km · Kalyan Bhiwandi RoadPrimary road 3.0 km · Kalyan - Shil RoadRailway line 437 mRailway station 397m away (Dombivli)Limited bus connectivity nearby
Water & environment
Water body 819 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Kalyan Dombivli Municipal Corporation

Municipal Corporation
Building Permit
Survey no. CTS No.2426, 2427 & 2428 Mauje- Dombivali, Dombivali (West).
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Kalyan Dombivli Municipal Corporation

Municipal corporation

Has approved 742 RERA projects3.7% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
585
On record
5,683 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.