Complete project overview

MahaRERA · Registration filing
Floors
16
Buildings
2
Parking
69 spaces
Land area
1,406 sq m
Sanctioned built-up
4,169 sq m

Timeline

RERA registeredFeb 2024
Proposed completionDec 2026
TodayJul 2026
Construction progress
Water Supply15%
Flat fit-out35%
OC-readiness90%
Water conservation…90%
Fire protection an…95%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Stairs & lifts100%
External finishes100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Landscaping & Tree…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

DIMPLE REALTORS PRIVATE LIMITED

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
5Projects
1City
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
365 homeson the public record across 5 projects
55,974 sq mbuilt-up filed
12,108 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Slum Rehabilitation AuthoritySlum Rehabilitation Authority2 of 3 projects
Municipal Corporation of Greater MumbaiMunicipal Corporationthis project1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Eksar
Taluka
Borivali
District
Mumbai Suburban
Pincode
400103
Survey no.
977, 977/1, 977/2
North boundary
Plot No 35
East boundary
Plot No 12
South boundary
44 Feet I C Colony Main Road
West boundary
30 Feet I C Colony Cross Road No 5
What’s nearby
Schools1 school within 1km · College or university 1.9km away · Library 1.8km away
HealthcareHospital 245m away · 1 clinic within 1km
Lifestyle1 park within 500m · Gym or sports centre 1.4km away · 20+ restaurants and cafes within 1km
ShoppingSupermarket 383m away · Convenience store within 500m · Bank 363m away
Getting around
Expressway 1.7 km · Western Express HighwayPrimary road 312 m · Link RoadRailway line 1.1 kmMetro station 524m away (Mandapeshwar - I.C. Colony)3 bus stops within 500m
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. 977, 977/1, 977/2
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.