HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
16
Buildings
2
Parking
106 spaces
Land area
3,458 sq m
Sanctioned built-up
13,492 sq m
Recreational open space
273 sq m

Timeline

RERA registeredSep 2023
Proposed completionApr 2026
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Aggregate area of …0%
Community Building…60%
Landscaping & Tree…90%
Street Lighting90%
Electrical meter r…90%
Internal finishes95%
OC-readiness95%
Internal Roads & F…95%
Sewerage (Chamber,…95%
Excavation100%
Basement (if any)100%
Plinth100%
Superstructure100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
Water Supply100%
Treatment And Disp…100%
Solid Waste Manage…100%
Water conservation…100%
Energy managemcnt100%
Fire protection an…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Diamond Nexus Associates

PartnershipPromoter type
Pune, MAHARASHTRABased in
4Projects
1City
2019–2026Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
295 homeson the public record across 4 projects
32,860 sq mbuilt-up filed
15,400 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Pimpari Chinchwad Municipal Coporationthis project1 of 2 projects
Pimpri Chinchwad Municipal CorporationMunicipal Corporation1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
CHARHOLI
Taluka
Haveli
District
Pune
Pincode
412105
Survey no.
543/1 & 546/2
North boundary
Property Of S No 546-1
East boundary
Property Of S No 543-2
South boundary
30 Mtr Wide Road
West boundary
Property Of S No 542 Old S No 1016
What’s nearby
SchoolsNearest school 1.4km away · College or university 1.6km away · Library 1.4km away
HealthcareHospital 61m away · 1 clinic within 1km
Lifestyle1 park within 500m · Swimming pool within 2km
ShoppingSupermarket 1.5km away · Mall 662m away · Bank 884m away
Getting around
Expressway 1.2 km · Don Bosco RoadPrimary road 62 m · National Games MargRailway line 3.4 kmMetro station 1.8km away (Ramwadi)2 bus stops within 500mAirport 3.8km away
Water & environment
Water body 662 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pimpari Chinchwad Municipal Coporation

Building Permit
Survey no. 543/1 & 546/2

The promised possession date (30 Apr 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.