Complete project overview

RERA Telangana · Registration filing
Units
25 units
Unit mix
25 × 2BHK
Saleable area
107–109 sq mper unit, as filed
Floors
5
Land area
957 sq m
Built-up area
2,205 sq m

Timeline

RERA approvedNov 2021
Proposed completionNov 2024
TodayJul 2026
Construction progress

90% overall, as filed

Podiums0%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

0 of 25 available
BuildingFloorTypeArea sq mAvailable
NLC AADYA12BHKmortgaged1080 of 1
NLC AADYA12BHK1090 of 1
NLC AADYA12BHK1080 of 1
NLC AADYA12BHK1070 of 1
NLC AADYA12BHK1070 of 1
NLC AADYA22BHK1080 of 1
NLC AADYA22BHKmortgaged1090 of 1
NLC AADYA22BHKmortgaged1080 of 1
NLC AADYA22BHK1070 of 1
NLC AADYA22BHK1070 of 1
NLC AADYA32BHK1080 of 1
NLC AADYA32BHK1090 of 1
NLC AADYA32BHK1080 of 1
NLC AADYA32BHK1070 of 1
NLC AADYA32BHK1070 of 1
NLC AADYA42BHK1080 of 1
NLC AADYA42BHK1090 of 1
NLC AADYA42BHK1080 of 1
NLC AADYA42BHK1070 of 1
NLC AADYA42BHK1070 of 1
NLC AADYA52BHK1080 of 1
NLC AADYA52BHK1090 of 1
NLC AADYA52BHK1080 of 1
NLC AADYA52BHK1070 of 1
NLC AADYA52BHK1070 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

NEWLAND CONSTRUCTIONS

PartnershipPromoter type
Hyderabad, TelanganaBased in
9Projects
1City
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
265 homeson the public record across 9 projects
35,713 sq mbuilt-up filed
11,013 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authority7 of 8 projects
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporationthis project1 of 8 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
AMEENPUR
Village
AMEENAPUR
Mandal
AMEENPUR
District
Sangareddy
Pincode
502032
North boundary
VENDORS LAND
East boundary
30 FT ROAD
South boundary
40 FT ROAD
West boundary
GOVT SCHOOL
What’s nearby
SchoolsNearest school 1.2km away · College or university 1.0km away
HealthcareHospital 985m away · Clinic within 2km
LifestylePark 713m away · Gym or sports centre 1.8km away · 5 restaurants and cafes within 1km
ShoppingSupermarket 1.1km away · Mall 1.1km away · Bank 987m away
Getting around
Expressway 1.0 kmPrimary road 1.2 kmRailway line 2.0 kmRailway station 2.1km away (Chandanagar)Limited bus connectivity nearby
Water & environment
Water body 263 m · HMWSSB Suraksha Colony Water Reservoir
distances only — not a flood assessment
Government land classification

No residential (House Sites) class on record. The state classes this village’s land as Dry land, Wet Land double crop. If it’s sold as residential plots, verify the layout’s conversion / approval.

Telangana Registration & Stamps
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit
Survey no. 343/16

The promised possession date (12 Nov 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.