Complete project overview

RERA Telangana · Registration filing
Units
160 units
Unit mix
160 × 3BHK
Saleable area
155–318 sq mper unit, as filed
Floors
10
Buildings
3
Land area
10,736 sq m
Built-up area
39,948 sq m

Timeline

RERA approvedMay 2023
Proposed completionMay 2028
TodayJul 2026
Construction progress

57.5% overall, as filed

Flat fit-out0%
External finishes0%
OC-readiness0%
Internal finishes15%
Stairs & lifts75%
Superstructure85%
Excavation100%
Basement & plinth100%
Podiums100%
Stilt floor100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

124 of 160 available
BuildingFloorTypeArea sq mAvailable
BLOCK A13BHKmortgaged2622 of 2
BLOCK A13BHKmortgaged2284 of 4
BLOCK A13BHKmortgaged1761 of 1
BLOCK A13BHKmortgaged2621 of 1
BLOCK A13BHKmortgaged2611 of 1
BLOCK A23BHKmortgaged2841 of 1
BLOCK A23BHKmortgaged2482 of 2
BLOCK A23BHKmortgaged1891 of 1
BLOCK A23BHKmortgaged3021 of 1
BLOCK A23BHKmortgaged3181 of 1
BLOCK A23BHKmortgaged2602 of 2
BLOCK A23BHKmortgaged2981 of 1
BLOCK A33BHKmortgaged2841 of 1
BLOCK A33BHKmortgaged2481 of 1
BLOCK A33BHKmortgaged1891 of 1
BLOCK A33BHKmortgaged3181 of 1
BLOCK A33BHKmortgaged2601 of 2
BLOCK A33BHKmortgaged2981 of 1
BLOCK A33BHK2480 of 1
BLOCK A33BHK3021 of 1
BLOCK A43BHKmortgaged2481 of 1
BLOCK A43BHK2481 of 1
BLOCK A43BHK2601 of 1
BLOCK A43BHKmortgaged2601 of 1
BLOCK A43BHKmortgaged2981 of 1
BLOCK A43BHKmortgaged1891 of 1
BLOCK A43BHKmortgaged3020 of 1
BLOCK A43BHKmortgaged2840 of 1
BLOCK A43BHKmortgaged3180 of 1
BLOCK A53BHK2482 of 2
BLOCK A53BHKmortgaged3021 of 1
BLOCK A53BHKmortgaged3181 of 1
BLOCK A53BHK2602 of 2
BLOCK A53BHKmortgaged2981 of 1
BLOCK A53BHKmortgaged2841 of 1
BLOCK A53BHK1890 of 1
BLOCK A63BHK2482 of 2
BLOCK A63BHK1891 of 1
BLOCK A63BHK2841 of 1
BLOCK A63BHK2602 of 2
BLOCK A63BHK2981 of 1
BLOCK A63BHK3021 of 1
BLOCK A63BHK3181 of 1
BLOCK A73BHKmortgaged2841 of 1
BLOCK A73BHKmortgaged2481 of 2
BLOCK A73BHK1891 of 1
BLOCK A73BHKmortgaged3021 of 1
BLOCK A73BHKmortgaged2601 of 2
BLOCK A73BHKmortgaged2981 of 1
BLOCK A73BHKmortgaged3180 of 1
BLOCK A83BHK2841 of 1
BLOCK A83BHK2482 of 2
BLOCK A83BHK3021 of 1
BLOCK A83BHK3181 of 1
BLOCK A83BHK2602 of 2
BLOCK A83BHK2981 of 1
BLOCK A83BHK1891 of 1
BLOCK A93BHKmortgaged2841 of 1
BLOCK A93BHK1891 of 1
BLOCK A93BHK3021 of 1
BLOCK A93BHK3181 of 1
BLOCK A93BHKmortgaged2981 of 1
BLOCK A93BHKmortgaged2600 of 2
BLOCK A93BHKmortgaged2481 of 2
BLOCK A103BHKmortgaged2841 of 1
BLOCK A103BHKmortgaged2481 of 2
BLOCK A103BHKmortgaged3181 of 1
BLOCK A103BHKmortgaged2981 of 1
BLOCK A103BHK1890 of 1
BLOCK A103BHKmortgaged2600 of 2
BLOCK A103BHK3020 of 1
BLOCK B13BHKmortgaged2621 of 1
BLOCK B13BHKmortgaged2561 of 1
BLOCK B13BHKmortgaged2031 of 1
BLOCK B13BHKmortgaged2551 of 1
BLOCK B13BHKmortgaged1551 of 1
BLOCK B13BHKmortgaged2031 of 1
BLOCK B13BHKmortgaged2621 of 1
BLOCK B23BHKmortgaged2881 of 1
BLOCK B23BHKmortgaged3141 of 1
BLOCK B23BHKmortgaged2231 of 1
BLOCK B23BHKmortgaged2971 of 1
BLOCK B23BHKmortgaged3031 of 1
BLOCK B23BHK2340 of 1
BLOCK B23BHKmortgaged1800 of 1
BLOCK B33BHKmortgaged3141 of 1
BLOCK B33BHKmortgaged2881 of 1
BLOCK B33BHKmortgaged2341 of 1
BLOCK B33BHKmortgaged1801 of 1
BLOCK B33BHKmortgaged3031 of 1
BLOCK B33BHKmortgaged2971 of 1
BLOCK B33BHKmortgaged2231 of 1
BLOCK B43BHK2881 of 1
BLOCK B43BHK2341 of 1
BLOCK B43BHK2231 of 1
BLOCK B43BHKmortgaged3031 of 1
BLOCK B43BHK1800 of 1
BLOCK B43BHKmortgaged3140 of 1
BLOCK B43BHK2971 of 1
BLOCK B53BHK2881 of 1
BLOCK B53BHK3141 of 1
BLOCK B53BHK1801 of 1
BLOCK B53BHK2341 of 1
BLOCK B53BHK3031 of 1
BLOCK B53BHK2231 of 1
BLOCK B53BHK2971 of 1
BLOCK B63BHK2881 of 1
BLOCK B63BHK3141 of 1
BLOCK B63BHK1801 of 1
BLOCK B63BHK2341 of 1
BLOCK B63BHK2231 of 1
BLOCK B63BHK2971 of 1
BLOCK B63BHKmortgaged3031 of 1
BLOCK B73BHK2881 of 1
BLOCK B73BHK3141 of 1
BLOCK B73BHK1801 of 1
BLOCK B73BHK2341 of 1
BLOCK B73BHK3031 of 1
BLOCK B73BHK2231 of 1
BLOCK B73BHK2971 of 1
BLOCK B83BHK2231 of 1
BLOCK B83BHK2341 of 1
BLOCK B83BHK2880 of 1
BLOCK B83BHK3030 of 1
BLOCK B83BHK1800 of 1
BLOCK B83BHKmortgaged3140 of 1
BLOCK B83BHKmortgaged2970 of 1
BLOCK B93BHKmortgaged2881 of 1
BLOCK B93BHKmortgaged3031 of 1
BLOCK B93BHK3140 of 1
BLOCK B93BHK1800 of 1
BLOCK B93BHK2340 of 1
BLOCK B93BHK2230 of 1
BLOCK B93BHKmortgaged2970 of 1
BLOCK B103BHKmortgaged2881 of 1
BLOCK B103BHK1800 of 1
BLOCK B103BHKmortgaged2340 of 1
BLOCK B103BHKmortgaged3030 of 1
BLOCK B103BHKmortgaged2230 of 1
BLOCK B103BHK3141 of 1
BLOCK B103BHKmortgaged2970 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

Sri Venkateshwara Developers

PartnershipPromoter type
Medchal-Malkajgiri, TelanganaBased in
7Projects
7Cities
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
270 homes · 545 plotson the public record across 7 projects
53,259 sq mbuilt-up filed
1,65,277 sq mplotted area
1,81,802 sq mland declared
₹4.26 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authoritythis project3 of 7 projects
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation2 of 7 projects
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)1 of 7 projects
Local Planning AuthorityTown & Country Planning (DTCP)1 of 7 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
Gundlapochampally Muncipality
Village
Gundlapochampally
Mandal
Medchal
District
Medchal-Malkajgiri
Pincode
500043
North boundary
Road
East boundary
Road
South boundary
Neighbours Land
West boundary
Neighbours Land
What’s nearby
Schools2 schools within 1km
HealthcareNearest hospital 3.0km away · Doctor's clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Bank 43m away
Getting around
Expressway 1.4 kmPrimary road 2.3 km · Medak RoadRailway line 744 mRailway station 845m away (Gundla Pochampally)Bus stop within 500m
Water & environment
Water body 238 m
distances only — not a flood assessment
Declared external development
Sewerage (Chamber,…60%
Community Building…40%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
CLUB HOUSE0%
Roads0%
Water supply0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Sewage0%
Solid waste0%
Rainwater0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit
Survey no. 41/1 & 48
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.