HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
4
Buildings
14
Land area
2,572 sq m
Sanctioned built-up
3,920 sq m
Recreational open space
258 sq m

Timeline

RERA registeredNov 2021
Proposed completionDec 2026
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Stilt floor0%
Treatment And Disp…0%
Excavation100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Internal Roads & F…100%
Water Supply100%
Sewerage (Chamber,…100%
Landscaping & Tree…100%
Street Lighting100%
Water conservation…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

AAHAN BUILDCON

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2021–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Donaje
Taluka
Haveli
District
Pune
Pincode
411025
Survey no.
PLOT NO 408
North boundary
PLOT NO 416 AND GAOTHAN PROPERTIES
East boundary
ZP ROAD
South boundary
WALTER D SAUZA
West boundary
GHERA SHINGAD BOUNDARY
What’s nearby
SchoolsNo schools within 2km · College or university 1.8km away
HealthcareNearest hospital 5.0km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 291 mNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 1.9 km · Khadakwasla ReservoirRiver 2.1 km · MuthaCanal 4.1 km · Mutha Right Bank Canal
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Town Planning

Building Permit
Survey no. PLOT NO 408
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Town Planning

Planning authority

Has approved 21 RERA projects0.1% of Maharashtra.

an apartments market71% apartments · 29% plotted layouts. Apartments like yours are this body's core business.

Builders
16
On record
466 flats · 542 plots
Reach
8 districts
Since
2017

More layout-heavy than Maharashtra overall — 29% plots here vs 5% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.