HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
1 spaces
Land area
1,200 sq m
Sanctioned built-up
2,237 sq m

Timeline

RERA registeredSep 2023
Proposed completionMar 2027
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Water Supply0%
Flat fit-out95%
Stairs & lifts95%
External finishes95%
Sewerage (Chamber,…95%
Storm Water Drains95%
Water conservation…95%
Fire protection an…95%
Electrical meter r…95%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
OC-readiness100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SAFAL ENTERPRISES

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2023–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
NANDIVALI
Taluka
Kalyan
District
Thane
Pincode
421201
Survey no.
PLOT BEARING SURVEY NO.36, HISSA NO.1Y, ADMEASURING 293 SQ MTR AND SURVEY NO. 36, HISSA NO. 1E, ADMESURING 907 SQ.MTR
North boundary
15 FEET WIDE ROAD
East boundary
BOUNDARY OF REVENUE VILLAGE G B PATHARLI
South boundary
PART OF PLOT NO 65 OF GANDINAGAR
West boundary
LAND OF S NO 32 H NO 2 9
What’s nearby
SchoolsNearest school 1.1km away
HealthcareHospital 460m away · Clinic within 2km · Pharmacy within 1km
LifestylePark 1.1km away · Gym or sports centre 575m away
ShoppingNo supermarket within 2km
Getting around
Primary road 1.4 km · Kalyan - Shil RoadRailway line 281 mRailway station 1.6km away (Kopar)Limited bus connectivity nearby
Water & environment
River 504 mWater body 576 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Kalyan Dombivli Municipal Corporation

Municipal Corporation
Building Permit
Survey no. PLOT BEARING SURVEY NO.36, HISSA NO.1Y, ADMEASURING 293 SQ MTR AND SURVEY NO. 36, HISSA NO. 1E, ADMESURING 907 SQ.MTR
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Kalyan Dombivli Municipal Corporation

Municipal corporation

Has approved 742 RERA projects3.7% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
585
On record
5,683 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.