Complete project overview

MahaRERA · Registration filing
Floors
20
Buildings
2
Parking
130 spaces
Land area
1,029 sq m
Sanctioned built-up
6,251 sq m

Timeline

RERA registeredOct 2025
Proposed completionDec 2028
TodayJul 2026
Construction progress
Internal finishes0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Treatment And Disp…0%
Solid Waste Manage…0%
Fire protection an…0%
Electrical meter r…0%
Superstructure20%
Stairs & lifts20%
Excavation100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

CHANDRATARA LAXMI REALTORS LLP

Limited Liability PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Mira-Bhayandar (M Corp.)
Taluka
Thane
District
Thane
Pincode
401107
Survey no.
survey No 60/1, village Navghar
North boundary
30M DP ROAD
East boundary
PLOT.NO.290/12
South boundary
PLOT.NO. 293/2
West boundary
12M EXISTING ROAD
What’s nearby
Schools2 schools within 1km
HealthcareHospital 287m away · 2 clinics within 1km
LifestylePark 1.8km away · Gym or sports centre 855m away · 6 restaurants and cafes within 1km
ShoppingSupermarket 965m away · Mall 1.8km away
Getting around
Expressway 2.0 km · Western Express HighwayPrimary road 1.1 km · Mira Bhayandar RoadRailway line 2.1 km · Western Railway Virar to BorivaliMetro station 1.9km away (Kashigaon)3 bus stops within 500m
Water & environment
Water body 310 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Mira Bhayndar Municipal Corporation

Municipal Corporation
Building Permit
Survey no. survey No 60/1, village Navghar
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation

A city municipal corporation that sanctions projects within its own limits. It has approved 12,653 RERA projects across 34 districts about 1 in 2 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.