HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
5
Buildings
2
Parking
26 spaces
Land area
500 sq m
Sanctioned built-up
681 sq m

Timeline

RERA registeredJan 2025
Proposed completionDec 2027
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Water Supply50%
Electrical meter r…50%
Flat fit-out90%
Sewerage (Chamber,…90%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SANJAY RAMCHANDRA DALAVI

IndividualPromoter type
Raigarh, MAHARASHTRABased in
2Projects
1City
2024–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2 projectson the public record across 2 projects
1,864 sq mbuilt-up filed
1,050 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Nagothane
Taluka
Roha
District
Raigarh
Pincode
402106
Survey no.
SURVEY NUMBER 6/1/B
North boundary
PROPERTY BY DHAMANE
East boundary
PROPERTY BY DILIP SHIRKE
South boundary
GRAM PANCHAYAT NAGOTHANE RAHDARICHA ROAD
West boundary
PROPERTY BY SANGALE
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 627m away · 1 clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 270 mPrimary road 671 mRailway line 302 mNo metro or railway within 5kmBus stop within 1km
Water & environment
Water body 69 mRiver 832 m · Amba
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.