Complete project overview

MahaRERA · Registration filing
Floors
40
Buildings
5
Parking
971 spaces
Land area
19,599 sq m
Sanctioned built-up
86,800 sq m
Recreational open space
4,338 sq m

Timeline

RERA registeredOct 2019
Proposed completionOct 2025
TodayJul 2026
Construction progress
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Open Parking0%
Superstructure8%
Stilt floor95%
Basement (if any)98%
Podiums98%
Plinth98%
Excavation100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

PEER REALTY PRIVATE LIMITED

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2019–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Taluka
Chavindra
District
Thane
Pincode
400610
Survey no.
New S No 56, H No 5 A 2, New S No. 56, H No 6 B Sector 4
North boundary
WASP Company
East boundary
20 M wide DP Road and Hiranandani Meadows
South boundary
Hiranandani Meadows
West boundary
Godrej Edewoods
What’s nearby
Schools1 school within 500m · 3 educational institutions within 1km · Library 1.7km away
HealthcareHospital 38m away · 2 clinics within 1km · Pharmacy within 500m
LifestylePark 789m away · Playground within 500m · Gym or sports centre 354m away
ShoppingSupermarket 49m away · Bank 47m away · ATM within 500m
Getting around
Expressway 1.2 km · Majiwada-Kapurbawdi FlyoverPrimary road 888 m · Eastern Express TurnpikeRailway line 2.2 kmMetro station 902m away (Kapurbawdi Station)12 bus stops within 500m
Water & environment
Water body 277 m
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

2 complaints on MahaRERA’s register for this project 1 disposed, 1 still open.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.