Complete project overview

MahaRERA · Registration filing
Units
26 units
Floors
6
Buildings
2
Parking
29 spaces
Land area
730 sq m
Sanctioned built-up
898 sq m

Timeline

RERA registeredDec 2024
Proposed completionDec 2026
TodaySep 2026
Construction progress
Podiums0%
Stilt floor0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Electrical meter r…0%
Open Parking0%
Excavation100%
Basement (if any)100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

P.G ENTERPRISES

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Badlapur (M Cl)
Taluka
Ambarnath
District
Thane
Pincode
421503
Survey no.
Survey No 56 Hissa No 12
North boundary
S No 56 H no 7
East boundary
S No 56 H No 11
South boundary
S No54
West boundary
9 MT Wide Road
What’s nearby
SchoolsNo schools within 2km · 3 educational institutions within 1km · Library 369m away
HealthcareHospital 153m away · 1 clinic within 1km · Pharmacy within 500m
LifestylePark 591m away · 8 restaurants and cafes within 1km
ShoppingNo supermarket within 2km · Convenience store within 1km · Bank 9m away
Getting around
Primary road 588 m · Pipeline RoadRailway line 43 mRailway station 223m away (Badlapur)3 bus stops within 500m
Water & environment
Water body 102 m · Mahalaxmi Lake
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹44,064per sq yd
₹52,700per sq m
Which rate
residential flat (built)
Matched to
The rate published for the village of “Badlapur (M Cl)”.
In force
2026-2027 schedule
Spread
₹41,639₹44,064 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Kbmc

Building Permit
Survey no. Survey No 56 Hissa No 12
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Kbmc

Planning authority

Has approved 21 RERA projects0.1% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
20
On record
234 flats · 0 plots
Since
2019

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

2,254 residential projects still under way within 25 km. Step out ring by ring:

100 projects within 1 km — showing the nearest 6.

BadlapurResidential / Group Housing

SHIVSHAKTI MANOHAR RESIDENCY

SHIVSHAKTI DEVELOPERS

Mar 2019registered
Dec 2026target completion
Government Guidance Rate₹44,064/sq ydScale138 flatsAuthorityMahaRERA
BadlapurResidential / Group Housing

Vedant Nakshatra Wing K Phase V

MOHAN HARDASMAL THARWANI

Jun 2023registered
Jun 2026target completion
Government Guidance Rate₹44,064/sq ydScale117 flatsAuthorityMahaRERA
BadlapurOthers

SINDHURAJ CO . OPP. HSG. SOC. LTD

ARC DEVELOPERS

Dec 2023registered
Dec 2026target completion
Government Guidance Rate₹44,064/sq ydScale29 flatsAuthorityMahaRERA
BadlapurOthers

SATISH OAK HEIGHT

SHREE SAI PRATHAMESH DEVELOPERS

Aug 2021registered
Mar 2026target completion
Government Guidance Rate₹44,064/sq ydScale116 flatsAuthorityMahaRERA
BadlapurResidential / Group Housing

Amrut Manjil

SAI SHRADHA DEVELOPERS

Feb 2023registered
Jan 2028target completion
Government Guidance Rate₹44,064/sq ydScale173 flatsAuthorityMahaRERA
BadlapurResidential / Group Housing

VISHWA SKY HIGH

VINEET INFRASTRUCTURE

Jan 2023registered
Nov 2027target completion
Government Guidance Rate₹44,064/sq ydScale102 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.