01
Complete project overview
MahaRERA · Registration filing- Floors
- 4
- Buildings
- 2
- Parking
- 16 spaces
- Land area
- 558 sq m
- Sanctioned built-up
- 871 sq m
Timeline
RERA registeredMar 2025
Proposed completionJun 2027
TodayJul 2026
Construction progressPer-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Excavation100%
Basement (if any)100%
02
Builder’s track record
MahaRERA · Promoter registrationPrachi Infra
PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
03
Location
MahaRERA · Registration filing- Village
- Pimpri Chinchawad (M Corp.)
- Taluka
- Haveli
- District
- Pune
- Pincode
- 411044
- Survey no.
- Plot No. 419 -A , Sector No. 27
- North boundary
- Open Land
- East boundary
- Plot No - 420B and Plot No - 420A
- South boundary
- 10 Point 50 Meter Road
- West boundary
- 24 Meter Wide Road
What’s nearby
Schools1 school within 1km
HealthcareHospital 988m away · 1 clinic within 1km
LifestylePark 928m away · Gym or sports centre 1.9km away · 4 restaurants and cafes within 1km
ShoppingNo supermarket within 2km
Getting around
Expressway 468 m · Old Pune–Mumbai HighwayPrimary road 353 mRailway line 1.3 km · Mumbai–Pune RailwayMetro station 1.0km away (Bhakti Shakti)Bus stop within 1km
Water & environment
Water body 608 m
distances only — not a flood assessmentLegal & regulatory recordFrom MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
LitigationNone declared to MahaRERA
None on record with MahaRERA against this project.
Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.